NASA STS Recordation
Oral History Project
Edited Oral History Transcript
Stephanie
S. Stilson
Interviewed by Jennifer Ross-Nazzal
Kennedy Space Center, Florida – 14 July 2011
Ross-Nazzal:
Today is July 14th, 2011. This interview is being conducted with Stephanie
Stilson at Kennedy Space Center, Florida, as part of the NASA STS
Recordation Oral History Project. The interviewer is Jennifer Ross-Nazzal.
Thanks again for making time to meet with me today. I certainly appreciate
it.
Stilson:
Absolutely. It’s a pleasure.
Ross-Nazzal:
I want to start by asking if you could give me an overview of your
career out here at Kennedy Space Center.
Stilson:
Sure. I actually started here at Kennedy as a cooperative education
student when I was in college at North Carolina State [University,
Raleigh, North Carolina] back in ’89. I had been to the visitor
center as a child, in the third grade, with my father, and said “Oh,
when I grow up I want to work for NASA.” So I went into science
and into engineering and eventually went to NC State. They were big
on the co-op program with their engineering program there. So lo and
behold, I’m looking through the opportunities, and there’s
NASA Kennedy Space Center. I immediately applied, and initially they
were not accepting. They didn’t have any openings. So I was
like well okay. I just moved on. Let me apply to some other companies.
Eventually I got a call out of the blue that they had an opening,
and would I like to come down to Kennedy. Of course I said yes.
So I started. The ironic thing is the first office I worked in as
a co-op was called Mission Planning. It’s actually the office
that I ended up in as a flow director for Discovery. So I went full
circle and came back. In the course of that I started off working
mission planning, building manifests for the Shuttle to show it flying
out to the year 2020. Here I was this young kid building these schedules
to show us flying to what, at the time, we thought was the end of
the program. That was 2020.
From there I spent three semesters—on and off back at school—working
in Mission Planning, doing that same kind of thing, but I wanted to
get more into hardware. The job I was currently in was all programming.
I really didn’t want to be a programmer. I was a computer engineering
major. Lot of folks see “computer” in the degree title
and think computer science, programming. I wanted to do hardware.
Based on some recommendations from some folks here, including Russell
[R.] Romanella, I went over to the Spacelab organization and started
working over there in payloads and spent some time there. Then eventually
once I graduated I started full-time with the Spacelab Program as
an electrical engineer. I double-majored in electrical and computer
engineering. I was doing testing of experiments that were going to
fly in Spacelab. That was really neat work, a lot of fun, but Spacelab
was coming to an end.
So I hung in there, I wanted to be there until we were completely
done with Spacelab. Then I just transitioned right over to Space Station
and was working power systems for Space Station. Eventually I got
to the point where I was what they call a test director for the multi-element
integration test team, which is basically the team at Kennedy that
processed all the different components of Space Station and tested
them on the ground to ensure that when we put them together on orbit
they were going to work properly.
I got to lead that team, and that was real fun and exciting work.
In the course of doing that I was actually spending some time in Huntsville
[Marshall Space Flight Center, Alabama] testing out the US Lab component
for the Space Station and met this gentleman named Mike [Michael D.]
Leinbach, who I found out later had grown up in the Shuttle Program
and was doing somewhat of a detail type of assignment with the Station
Program.
I got along very well with him. Obviously he saw something in me that
he liked because he started having some conversations with me, “Hey
you might want to come over to Shuttle. We’re doing great things
over there, and you might really like that.” So I saw that as
a great opportunity. It was going to be a big change but a good opportunity.
That’s how I joined Discovery’s team. I went through the
interview process for an opening that they happened to have. At the
time it was a vehicle manager position, because we did not have flow
directors at that point in time.
Kennedy had gone through a reorg [reorganization] where the position
of flow directors, which we had in the past, was downgraded to a vehicle
manager role. Eventually the flow director role was reinstated. So
I started out as vehicle manager but was still the team lead from
the NASA perspective of Discovery’s team.
Ross-Nazzal:
How did you come up to speed so quickly on such a complicated vehicle?
Stilson:
I was just talking about this yesterday with someone. There’s
no one person out here that knows everything about any of these Orbiters.
That’s what makes it such a team environment, you really have
to rely on everybody to know their little piece of it. There are over
30 systems on the vehicle itself. I don’t have to know everything
about the Orbiter itself, because I have such a strong team and they
do know everything about their little pieces.
That’s how we operate. So really I can’t tell you the
inner workings of every system at all. I can tell you on a high level
what they do, but when we get into a technical issue or something
that needs real down and in-depth discussion I turn to the technical
experts to do that.
Ross-Nazzal:
Did you have any sort of on-the-job training? Were you shadowing the
person who was the previous vehicle manager?
Stilson:
I somewhat got thrown right into it. It was really more like drinking
from a fire hose kind of approach at the time. When I came into the
first processing flow they were midway through the OPF [Orbiter Processing
Facility] flow when I joined the team. The Orbiter Processing Facility
flow is really the most complicated of the entire Shuttle processing
flow that we have here at Kennedy. You’ve got the processing
of the Orbiter, the boosters and the tank, which I’m involved
with all of that, but the most complex is the Orbiter obviously because
it’s the most complex part of the STS. So the team was right
in the middle of that.
I didn’t know the people. I didn’t know the acronyms.
I didn’t know the process. I went from an environment in payloads
where I basically grew up over there—and if I didn’t know
the answer I knew exactly who to go to to get the answer—to
being over here and really knowing no one. That was difficult. It
was a very challenging time. I spent a lot of time just talking to
people and asking questions. I knew that I was asking dumb questions,
I’m sure to them. A lot of the people I worked with had been
working Shuttle since STS-1.
My contractor counterpart at the time was Gene Nurnberg, who had been
here since Apollo days. He is a wealth of knowledge, but because he
was an old-timer, he wasn’t real anxious to spend a lot of time
training not just a newbie to the Shuttle Program but a young person
and a female. He came from the old school. It was, I think, a shock
for him to all of a sudden have a counterpart like me. I was very
much inferior to him when it came to knowing what was going on.
So really it was just over time, just absorbing, talking to people.
The other difference that was very challenging is in Station we had
a different setup in regards to how the contractor operated. We didn’t
have a prime contractor. NASA pretty much ran everything. We had contractor
support, but when I was a test director over there I ran all the meetings.
I was the main person doing that part of the task. Where over here
we let our contractor counterpart do that. So I’m a part of
those meetings but I’m not necessarily the one running them
or building the schedule or anything of that nature. I’m doing
more oversight in Shuttle than I did in Station. So that was a big
change for me, especially a type A personality like me that feels
like I need to have full control. It was a big change for me to really
feel comfortable with having someone else basically running things
and me being able to stay engaged enough to really be part owner of
that schedule, but that is what I had to do. We worked together so
I had to sign up to that schedule, but I didn’t know the down
and in details to it like the contractor did. So that was a challenge.
Besides just spending time with the team, and absorbing what I could
from them, it was really the basic OJT [On the Job Training]. There
weren’t really training classes that I took to say here’s
how you become a vehicle manager or a flow director or anything like
that.
Ross-Nazzal:
You mentioned something that I thought was interesting, and I did
want to ask you at some point. Since you brought it up, you mentioned
you were a woman, and you were working with these guys. It seems like
this is very much a male environment with all the technicians here
and the engineers. Are there many women who work in the OPF?
Stilson:
It has changed a lot even since I’ve been here. I’ve been
with Discovery for 11 years now, so I have seen quite a bit of change.
In fact even now we have three female flow directors. That has never
happened in the past. There was one point in time where all of our
NASA vehicle managers, which is the next step down from flow director,
were all females. In the past that had never happened.
Definitely at that time there were not a lot of females in the workforce,
but there were more I think than maybe in some private industry companies
because there were quite a few. Even technicians, we’ve got
some great female technicians as well. But the males did outnumber
females overall on the team for sure.
Ross-Nazzal:
Tell us a little bit about Discovery itself. What makes it unique
from all of the rest of the fleet?
Stilson:
I get asked that question. I do a lot of media type events and so
forth and interviews. I get that question a lot. From a vehicle capability
perspective and how it looks, there’s really not much difference.
There are a couple things. From a technical perspective, Discovery
has the Station-to-Shuttle Power Transfer System, which allows us
to stay on orbit longer. When we’re docked to Station we can
feed off their power as opposed to using our internal power sources.
We have that and Endeavour has that. Atlantis does not. So that’s
one of the differences.
There’s something called three-string GPS [Global Positioning
System], which is a communications system, that Discovery and Atlantis
do not have but Endeavour does. So there’s some differences
between the Orbiters like that. Really when I think about the difference
in the vehicles, it’s more about the team in the sense that
I feel like Discovery basically lives through the team. That’s
what makes Discovery a living being. A lot of people think of it like
that, think of Discovery as our child, and we’ve been taking
care of it all this time. We nurture it and look after it. Soon we’re
going to be sending it off to college is how I’ve been looking
at the fact that we’re transferring it over to the Smithsonian
[Air and Space Museum, Steven F. Udvar-Hazy Center, Virginia]. It’s
time to let it leave the nest.
So the team for Discovery and each vehicle, their team has a persona
that’s a little bit different. Discovery has been known as the
workhorse of the fleet. There are several reasons for that. We’ve
done both return to flight missions. We’ve delivered the Hubble
Space Telescope. We’re the oldest. We’re the heaviest
because of being the oldest. Some people call it the hog. I’ve
heard that term as well.
In regards to the team I see us as a really get the job done, we’re
not here to mess around, let’s get going, we’ve got a
job to do, we’ve got to move on, let’s get this flight
under our belt and move on to the next one. That’s been the
impression I get from our team, and I like that. That’s somewhat
my attitude as well. So I think that’s really how, when I think
of Discovery, I think more about the team and all the work they’ve
done and how they’ve approached the challenges that we’ve
had over the years.
Ross-Nazzal:
Walk me through if you can how you process the vehicle. It’s
a complicated machine. It takes much longer than they originally anticipated.
They thought the OPF was going to be like maybe a day place for Shuttle
then it was going to move on.
Stilson:
Right. Yes. We use 125 days is what I’ll call our baseline for
the amount of time that the Orbiter spends in the Orbiter Processing
Facility. I like to compare an OPF to a garage for a car, because
that’s really what it is. It’s the best place, if you’re
going to do any type of work on an Orbiter, you want to do it in the
OPF. That’s its home. That’s the best place to do it.
During the process of a normal flow through the OPF, the main thing
we’re doing is system testing and checkout to ensure that those
systems are still functioning properly for the next mission. We spend
a lot of time working towards requirements. We have set requirements,
about 4,000 requirements for every flow that we have to go in and
meet. We do that using written procedures.
Everything we do here at Kennedy, we’re very much into documentation
and records and being able to prove that here’s what we were
supposed to do and here’s what we did. There are a lot of reasons
for that. An obvious reason would be we want to make sure we do it
right. Then heaven forbid if something were to happen and we had something
go wrong, we want to be able to go back and see. Okay. What did we
do? Did we do what we were supposed to do? Was that not the right
thing to do? So we want that traceability as well. We’re very
in tune to documenting everything we do.
The first step once we tow from the runway into the OPF is to get
that vehicle into a safe configuration so that the masses can come
work on it, because initially there are hazards that are still active
on the vehicle. So we go through that process. Getting all the platforms
in place. Getting access so the technicians can get into the ship.
Then a couple different things happen in parallel. We start the download
of the payload from the previous mission, whatever payload flew before.
If we have to remove a module, or change out panels, remove longerons,
those kinds of things, that all happens right away. Then we start
the process of uploading for the next payload. Preparing the payload
bay for that next payload that normally doesn’t get installed
until we get out to the launch pad, but there’s a lot of work
that happens in the midbody as well as the crew module to get ready
for the next payload that’s going in.
In parallel with that is all that system checkout and testing for
all the systems. We don’t go in and test every aspect of every
system. That’s why we have requirements based on what those
system experts feel are at a high risk of potentially not working
properly or if it’s a Crit [Criticality] 1, something that’s
very important that it works the first time. Those are things that
we’re going in and checking along the way.
We’re also doing problem resolution. So if on orbit we had an
issue, something didn’t work right, obviously we’re going
in and fixing that or troubleshooting that to determine what we have
to do to fix it. Then also along the way, as we’re doing testing,
we are finding problems. That’s why we’re doing the testing,
to find and then repairing those problems.
Another aspect of the processing flow that takes a lot of time is
inspections. We do a full inspection of the outer surface of the vehicle.
That’s blankets and tiles, reinforced carbon-carbon [RCC] panels
and so forth. When I say inspections, technicians and quality inspectors
are going in with a magnifying glass and looking at every thread point
on those blankets. So every little knot of thread they’re looking
to see is there any fraying going on. The black tile, they’re
very easy to break. So they’re going in and looking for any
damage that might have occurred. They’re having to measure that
damage and determine from the size of it, “Can we go in and
just repair it, or do we have to replace that entire tile?”
There’s certain criteria that has to be evaluated before we
can make that decision.
The critical path for us while in the OPF is usually through the aft.
Engines are one of the first things that we do. Pull the main engines
out. Send them over to the engine shop, and they recycle them over
there. Then also the TPS [Thermal Protection System] work, the tile
work, is usually worked throughout the entire Orbiter processing flow,
and then sometimes even into the VAB [Vehicle Assembly Building],
depending on how much we have to do.
We end up usually pulling—it’s ironic. The number of tile
that we usually remove from the vehicle correlates to the number of
days we’re in the Orbiter Processing Facility. I’m not
really sure why that is. When we try to predict how much tile work
we’re going to have, that’s the generic baseline that
we use. So we spend a lot of time working tile throughout the entire
processing flow.
Ross-Nazzal:
You mentioned Crit 1 criticalities. What would be a Crit 1 criticality
that you would have to investigate?
Stilson:
Main one that jumps out would be landing gear. You’re not going
to be able to land if your gear doesn’t deploy. We have a landing
gear functional that we go through that ensures that that system is
going to work properly. We have redundancy for I would say almost
every system in the vehicle, whether it’s double redundancy
or triple. So in most cases your Crit 1 systems have triple redundancy.
Another thing would be when we jettison the tank from the Orbiter.
Obviously if you’re going up during liftoff and you can’t
release that tank, that’s a bad day. So systems like that have
critical functions. Opening and closing payload bay doors is another
example, because once we get those doors open on orbit, if we can’t
close them, we can’t return until we close those doors.
Ross-Nazzal:
Tell me about that first mission where you were vehicle manager, and
you were officially in charge, you started from the moment of landing
until launch.
Stilson:
The first one I actually came in in the middle of the OPF flow. Good
or bad, I don’t know. It was very overwhelming for me at that
point in time. I really was more just in receiving mode as opposed
to contributing to the team, because I really wasn’t prepared
to do that. Now obviously there were other people looking out for
me. Kelvin [M.] Manning was my lead flow director, lead vehicle manager
at the time. I wasn’t completely thrown out to the wolves. There
were many people that were keeping an eye on things. Not just for
my benefit but ensuring that things were being done correctly.
That timeframe is all a blur to me. The main thing I remember is meeting
the team, not sitting in the right chair during one of the first meetings.
They had assigned seats, where I was supposed to be, and I didn’t
know that, and I was quickly told that was not my seat and I needed
to move over here. I think it was difficult for the team also, because
once again most of the people that I worked with had been working
Shuttle their whole career. Not many people had transitioned from
payloads to Shuttle.
We had plenty of people come from Shuttle to payloads. A lot of that
happened when the Shuttle Program changed the contract and went to
the prime contractor concept. At that point, Shuttle had a lot of
NASA personnel but didn’t have as much work for them as they
had previously, so a lot of those folks influxed over to Station.
But not many people transferred the other way.
Shuttle teams here take a lot of pride in the fact that they’ve
been doing this work for a very long time. This is their life. So
when newcomers come in it’s not a real easy change for them
either. But once again I had a lot of folks that were willing to help
me and guide me and really create an environment that I could learn
and understand things better.
We didn’t have the best relationship with our contractor at
that point in time, looking back on it now. Of course at the time
I didn’t know that that wasn’t normal. There wasn’t
a lot of trust then between NASA and the contractor.
Ross-Nazzal:
That’s Boeing?
Stilson:
That was USA (United Space Alliance). I don’t know really why
that was, because I came into that new. It was very obvious that it
wasn’t a comfortable situation, like we have now. So that’s
one of the things—we have really grown in that respect in the
sense that it was, I want to say an us against them environment back
then. The contractor wasn’t real anxious to share with NASA.
It was more of I’d have to really insert myself to gain knowledge.
Now I have a great relationship with my counterpart, and we share
everything. We have that trust. If it’s something that he doesn’t
want me to elevate right away, we work together to determine the right
time to do that. It’s a much more enjoyable environment. That’s
something that has progressed. Some of that could be personality-driven.
It could be environment-driven. Whatever it is, I’m just glad
that we’ve gotten to where we are. Even though I’m speaking
for the Discovery team, I know that’s the same with the other
vehicle teams as well. We all get along very well and work very well
together.
Ross-Nazzal:
Tell me about the lessons that you learned from that first flight
that you applied then to the flight that you managed the entire flight.
Stilson:
The main thing I learned from the first one was to really listen and
be in receive mode. In my previous role before Shuttle I was very
much in a transmit mode because of the function I had and because
of the knowledge I had. That was a little bit of an adjustment for
me, to really need to just sit back and listen, and not necessarily
be the person in charge of the meeting, and be the person to point
which way we were going to go. Sit back and let that happen. Insert
myself when needed, but realizing that that need wasn’t there
as much as it had been with some of my previous roles.
Ross-Nazzal:
How do you keep apprised of all the technical and engineering challenges
that are occurring on the floor? As you pointed out there are plenty.
There are major systems down there.
Stilson:
Absolutely. The main thing that happens is we have a good communication
structure that when something happens, if we find a problem, something’s
not working right, we immediately get that feedback from those folks.
First of all the ones on the floor report it. The technicians report
it to the engineers. The system engineers then report it to our integration
engineers, who then pass that along to me. I have an Orbiter Project
engineer. Basically the way we’re set up is your flow director
is your primary lead for the team—I’m talking only the
NASA structure—from the NASA side. Then I’ll call my left-
and my right-hand people: a NASA vehicle manager who covers the ops
[operations] side of things, looking at schedule, looking at when
tasks are supposed to happen, did they happen on time, why didn’t
they happen on time kind of thing, and then I’ve got the Orbiter
Project engineer, who integrates all the technical work. He or she
speaks for all those system engineers. So that’s my conduit.
The system engineers bubble that up to him, who then can really translate
that to me. I don’t need to know all those low level details.
I need to understand what’s the problem, and what do we need
to do to go fix it, and how long is that going to take. The NASA vehicle
manager and the Orbiter Project engineer work together to come to
that answer.
Ross-Nazzal:
Tell me about what impact budgets and schedules have on your position.
Stilson:
I really have never had to deal with the budget side of things before
now. That’s something that’s new now that I’m doing
transition and retirement of the Orbiters. As Discovery’s flow
director I was fortunate to really be sheltered from that. Pretty
much what we needed we got. The only time we really dealt with what
I’ll call budget-related concerns would be from a resource allocation
perspective.
When you have three vehicles flying, you have a top priority vehicle,
second, and what we call third in flow. If you’re the first
vehicle, the top priority vehicle, you’re pretty much going
to get whatever you need, because it’s our overall goal to ensure
you make your manifest target before the next one can fly. Being second
and third, then you’re taking what you can get in some cases
depending on what resources are available.
Once again, I didn’t really deal so much with budget. But as
we’re seeing now, as our workforce goes down because we’re
transitioning out of a program, and closing down a program, I’m
having to deal with less resources, and that’s always a challenge
for someone in a job like mine. Resources are one of the critical
tools that I use. So if you take those resources away from me then
that obviously makes my job more complicated, because now I’m
having to balance even more than usual. If we don’t have the
people to do it today, when will we have those people? What does that
mean to our overall schedule?
As a flow director, that’s really the primary function as I
see it. We’ve been given an end goal to launch on a certain
day. We’re going to do everything we can to do that safely and
with a sound vehicle. So that’s the balance. We’ve got
a certain amount of time that we anticipate needing to do the work.
Does that fit with what the goal of the agency is as to when they
would like us to launch? Then how do we manage that or maybe feed
back to them, “Hey you didn’t give us enough time and
here’s why? We hit this technical problem, it’s going
to take three weeks to fix, and my overall end date is going to move
out. Therefore I have no contingency.” As a flow director that’s
really to me the important thing that we manage and communicate. If
I can do what you’re asking me to do, great, that’s easy.
If I can’t, how do I go explain that? What do I do to hopefully
mitigate the impacts on the end?
Ross-Nazzal:
How closely are you working with some of the other element managers?
What impact might a delay with the SRBs [Solid Rocket Boosters] or
the ET [External Tank] have on your processing?
Stilson:
Flow director role starts from the minute the Orbiter lands, Discovery
in my case, until Discovery launches again. Although my primary focus
is on the Orbiter, I still have management responsibility for the
boosters and the tank as well.
Now fortunately I have very capable people, a NASA vehicle manager
for the ET and SRB that handles that for most of the time. When the
Orbiter is in the Orbiter Processing Facility most of my focus is
on the Orbiter unless there’s a technical issue or something
that arises that needs my attention on the boosters and tank. Until
then, they pretty much operate stand-alone without much impact to
me or from me.
Once we go integrated then I have more involvement with booster and
tank. Just the nature of now you’re coming down to the last
month of the flow. We’re putting all those elements together.
They’re all talking. There’s more likelihood that now
you’re going to see a problem that can possibly impact your
launch date.
If things are going well for the booster and the tank, I don’t
have a lot of involvement with those particular project leads or project
managers. The vehicle manager assigned to that task does. But say
for instance STS-133, where we had all the issues with the tank, I
did have a lot of interaction at that point in time because of the
high level impact of what that problem meant and what we were going
to do to go fix that problem.
Ross-Nazzal:
Can you talk some more about that flight and the external tank issues?
Stilson:
That’s definitely going to be one of my most memorable missions,
not just because it was my last one, but because so much happened.
Really I don’t know if we jinxed ourselves or what, but the
OPF flow was very generic. It makes sense. It’s our last one.
You’re not doing a bunch of modifications. Over the course of
time a lot of the challenges for an OPF flow would be new modifications,
late requirements, and things coming at the last minute. “Hey
we’ve got to go do this, can you still make your rollout date?”
Those were the challenges that we faced.
Obviously for Discovery’s last flow, we didn’t have that.
It was a pretty, what I call, vanilla flow. It went very well. We
didn’t have any real major challenges along the way. Then of
course we go integrated. We find the issues with the tank, which surprised
everybody, nobody was expecting to see that.
That was the first real big effort with the tank that I had been involved
with of that magnitude. Once again, different people, people I wasn’t
necessarily used to interacting with. Different contractor in the
sense of Lockheed Martin was now coming here and doing work. That
didn’t normally happen. So now we’re not only just integrating
with our USA and Boeing counterparts, we’re now also integrating
with Lockheed Martin as well.
It went really well. For the amount of work that had to happen and
the challenges that were put in front of the team, I was just constantly
amazed at how well everybody handled it. It was a very stressful situation.
The work we do here is stressful. There is pressure. A lot of people
don’t like to use that “pressure” word. It’s
become—schedule pressure—a negative word with a lot of
folks. I think I heard Mike Leinbach, the first person to say it,
“It’s not schedule pressure, it’s schedule awareness.”
We have to be aware of the schedule. There are reasons we have a schedule.
That’s an important part of what we do here at Kennedy, is process
to schedules. We shouldn’t be afraid of them, and we shouldn’t
see schedules as a negative thing.
Now can a schedule become negative if you let it? Absolutely. If you
put schedule above safety, above the technical aspects of the vehicle
being your top priority, then of course. It’s that three-legged
stool. You have to balance all of it together, but schedule is a very
big part of that. We can’t forget about the schedule. After
the accident of course we had a lot of talk about schedule pressure.
One of the examples I used to give, talking to my team was—say
you have kids. They have to be to school in the morning, so they have
to meet the school bus. You have a schedule then, right? You have
to get up at a certain time. You’ve got to eat breakfast a certain
time; you’ve got to get out to the bus. If you don’t have
that schedule, you’re not going to make the bus. You’re
not going to get to school. That’s a bad thing. Schedule pressure
is always there. It doesn’t have to be bad. It really should
be good, because that allows us a target to work to.
If we at Kennedy didn’t work towards schedules, we’d never
launch. You’d never get there. So I’m very passionate
about schedules obviously. I want people to see them as the good that
they are. But once again I will reinforce that schedules should never
cause us to sacrifice safety or get in the way of the technical needs
for operating the vehicle and mission success. We look at safety for
the crew first, and then mission success after that. Then the ground
processing would be third.
Ross-Nazzal:
Did you ever feel any pressure from JSC [Johnson Space Center, Houston,
Texas] or [NASA] Headquarters [Washington, DC] to get that vehicle
off the pad? Or were they insistent that we have to fly safely, whatever
resolution comes? If it comes six months later, then so be it?
Stilson:
It was both. Definitely felt both, because I knew that they were expecting
me to be ready by a certain date. If I couldn’t, they were going
to listen and understand why, but they were also going to challenge.
It wasn’t going to be an easy task. If I were going to come
in and say, “Oh guess what, guys, we need to slip launch a month,”
it wasn’t going to be, “Okay Steph, that’s fine.
Let’s just go slip launch.” I was going to have to justify
why that was and explain to them what options I had looked at and
why there was no other option but to slip.
Now, it usually wasn’t a month timeframe, maybe it’d be
a couple days or whatnot. But they would also want to make sure that
technically we were doing the right thing. The way we’re set
up is the folks in the Orbiter Project Office [OPO] at JSC are the
requirements owners. To me it’s a healthy balance because OPO
is pushing that hey, we need to do this mod [modification], or we
need to do whatever it is, this special test. That’s their goal.
That’s their job, to make sure we’re doing what we need
to do from a requirements perspective.
It’s my job to then push back and say, “Okay, if you want
to do that this is going to be the result. Program, you need to weigh
that risk and decide. Is it that important to do this modification,
knowing that it’s going to then impact this milestone? If it
is, great, we’ll go change the schedule, and we’ll move
it. But program, you need to understand my job is to tell you the
impacts of doing this work.”
We got into a mode after return to flight that I call the polishing
the apple scenario where it was a real struggle, because we had become
ultraconservative, obviously for a good reason. We had had an accident.
We needed to be ultraconservative to make sure that did not happen
again. As we continued to move forward and come up with new modifications
and so forth, I saw where there was work that you really had to ask
yourself, “Is this really necessary for safety of flight or
for mission success?”
If it’s not, do we really want to take the time and money to
do this now? Or is it something maybe we can do on the next flight
or a future flight? Of course, that point in time, we weren’t
thinking about the end of the program. We were thinking we need to
get back to flying again, and we’ll continue to get better.
Our goal was always to make that next flight better than the previous,
always moving forward.
So to me we got, as an agency and as a program, in a little bit of
a paralysis of feeling like oh my gosh if we don’t do everything
that people put in front of us then we’re not doing the right
thing. Well, if you take on everything, you’re never going to
fly again. I could sit here on the ground and continue to modify this
vehicle forever. You’ve got to pick a point that says okay we’ve
done what we need to do to lower that risk to an acceptable level.
Now we need to fly.
That was a challenging time, especially for someone like me. It’s
my job to get the work done, tell me what I have to do, but at some
point you got to quit giving me work if you want me to finish. That
was difficult because before then we had not operated where we were
getting so many real-time changes so quickly. Normally when we have
modifications, there have been years and years of discussion as to
what we’re going to do, when we’re going to do it, how
we’re going to implement it. We’d have that plan in place
before we started that flow.
After return to flight, we were getting those modifications real-time
because obviously we had a lot of big changes we wanted to make. So
implementing those real-time was very different for us and quite a
challenge.
Ross-Nazzal:
Let’s talk about [the Space Shuttle] Columbia [accident, STS-107].
What impact did it have on you? What involvement did you have in the
investigation and recovery?
Stilson:
The day the accident happened, I was actually doing some OJT, some
training in the firing room for landing. I was sitting with the test
directors learning what they do, what their role is for landing.
I really wasn’t familiar with that aspect of it. I had not sat
on console for landing previously. We were hearing, of course, the
voice loop about the indicators that they were seeing. Nobody initially
thought much of it. They thought “Ah, it’s instrumentation.”
There’s a lot of vibration going on when you’re coming
in. It’s not surprising to have some data dropouts and so forth.
I had no clue at all. Then as they kept discussing it, I was noticing
that the people around me were looking more and more tense.
I could tell. “Okay, something’s odd. Something’s
not quite the way it’s supposed to be.” The fact of having
a catastrophe like that was nowhere in my mind at all. When we realized
we weren’t having any communication with the vehicle my first
thought was. “Okay. They’ve landed out west in the desert
somewhere. We’re just not able to talk to them. We’re
going to have to go recover the vehicle and get out there, and get
the crew out.” Once again not thinking we would ever lose a
vehicle or a crew or anything.
Then we got the call saying that folks were visually seeing the breakup
of the vehicle and that it was on TV. Normally in the firing rooms
we have access to all the channels, but during critical operations
they block out the non-work related channels. So we just have mostly
our video cameras, Weather Channel, things like that.
The test directors immediately said, “Hey we need to get this
patched in” but it took some time. The people in the firing
room were still not seeing the video. We still weren’t quite
understanding what was happening.
The launch director, the Administrator at the time [Sean O’Keefe],
and the flow director at the time were already out at the landing
strip. That’s where they are at touchdown. So of course when
we realize we’re not landing, they send word that they’re
coming back. Well, because I’m the only person there that doesn’t
have a function, I’m just there to observe, they said, “Hey,
Steph. They’re all coming back here. They’re going to
need headsets. Run down to the comm [communication] room and get some
extra headsets so we can have them tied in.”
I go down to the comm room, and sure enough they’ve got CNN
[Cable News Network] up. There they show the breakup across the sky.
I immediately come back and say, “Guys, I just saw it on TV;
it was a complete breakup.” I was the one to tell them what
was being shown out on the airwaves. We went into lockdown mode just
like they did at JSC and reacted from there.
In regards to the recovery effort, I did spend some time out at Nacogdoches
[Texas] as the, we called it the hangar lead for the recovery efforts.
My role with that was to coordinate the team that was taking in debris
as we received it, trying to classify it, if we could identify what
it was. Get it packaged up to ship it to Barksdale [Air Force Base,
Louisiana] where it then was shipped back to KSC. We had an assembly
line process to do that.
Another big part of my job was to talk to the field walkers—and
this was the part that I really enjoyed the most. Every morning I
got to go speak to all the people that were walking the fields. Remember,
it was cold and rainy and miserable. It was terrible. Even in the
hangar we didn’t have any climate control. We were bringing
in big gas heaters to try and make it more comfortable for the team.
Everybody had parkas on. We’re on a concrete floor. No chairs.
No tables. We had all this stuff that we were trying to pull together
just on the fly. So in the mornings I’d go to a stadium where
I believe they held rodeos and bull riding. It was a big outdoor arena
with dirt.
It had bleacher seats filled with all these people from the National
Park Service and the fire walkers, and anybody who was a part of the
process. Every government agency represented out there: FBI [Federal
Bureau of Investigation], EPA [Environmental Protection Agency], FEMA
[Federal Emergency Management Agency] and so forth.
I’d get to talk to them about basically what was the latest
status. What had we found? Did it mean anything? Where are we concentrating
our efforts? Those kinds of things. These people were sleeping in
tents. By the time I got there they had been doing it for weeks on
end.
You could tell a lot of them were just worn-down. It was my responsibility
to try to motivate them, to tell them how important what they were
doing was to NASA. They’re walking through briars up to their
armpits every day and looking for little tiny pieces of whatever they
could pick up.
It was my job to motivate them and get them pumped up. “Hey,
Nacogdoches is going to be the site that finds the key to all this.
We’re going to be the ones to figure this out so that we can
find the problem, fix the problem, and start flying again.”
Meeting all those people, and seeing how there was such an outpour
from every person involved at every level to want to help. Something
as simple as bringing in ice cream for the team so they’d have
a treat—the local vendors did things like that. It was a really
good feeling.
It’ll always be a fond memory. Even though it was a very tragic
thing that happened I have a lot of good memories of that because
of the way people pulled together. I think that really is a tribute
to the crew and to what the crew meant to not just NASA, but to our
whole country. Everybody was willing to stop everything they were
doing and say how can we help get through this? It was a very emotional
time, but also a very rewarding time, to be a part of that process.
Ross-Nazzal:
What did you do when you came back to KSC?
Stilson:
Ironically enough, Discovery was in its Orbiter Maintenance Down Period
[OMDP], which is a scheduled maintenance period that we do. I believe
it’s every seven flights, eight years, something along those
lines, I can’t remember exactly when. We have a set period of
time that we do it.
So we were already in the process of taking the vehicle apart to do
in-depth inspections: wiring inspections, structural inspections to
do major modifications. We were doing the MEDS, the Multifunction
Electronic Display System, glass cockpit, and the other big one that
was already scheduled. I don’t remember; I’ll have to
come back to it.
We were doing modifications of all levels. Inspections and looking
for corrosion, which was part of the structural inspections. We were
already planning to be basically grounded for about a year, when the
accident happened.
Initially all work stopped; we all stopped. Then we as the Discovery
team quickly got back to work, because we were really the only vehicle
team that could work. We had to complete the maintenance period no
matter what. We had a huge amount of work to get as opposed to Endeavour
or Atlantis, who didn’t know when they were going to fly or
what their mission was going to be. I think that was very fortunate
for our team, because it gave us something to focus on. It wasn’t
just a matter of us sitting back waiting to hear what was going to
come out of the CAIB [Columbia Accident Investigation Board], what
was going to come out of the restoration effort here. “Hey guys
we can focus on this. We have real good work to do here.” I
think that was very helpful to the team. That’s what we did.
Once the CAIB report came out and we figured out what the problem
was, that then drove a bunch of additional modifications that we did
on the vehicle. The main one being installation of the Orbiter Boom
Sensor System so that we could do the inspections on orbit that we
had not been able to do in the past.
Also the Wing Leading Edge Sensor System. We went in and put sensors
on the spar of the leading edges of the wings, underneath the reinforced
carbon-carbon panels, that would allow us to detect if we had any
type of impact. At least we would know that right after liftoff or
on orbit if something happened to hit on orbit, and know where to
go look in case there was a breach.
Reinforced carbon-carbon had a lot of scrutiny as to are we doing
enough to test it and screen it to make sure there are no flaws that
could cause a break in the carbon-carbon panels. So we came up with
a thermography technique that basically scans and looks for any minute
flaws. Then of course anything we found had to be addressed as to
is this acceptable or not acceptable? That’s all handled by
the engineering team in Houston, but we did the work of doing the
scans and gathering that data.
Last one I’d mention would be the Boeing Rigid Insulation tile,
a new tile was created. It was a much stronger tile. Right now you
can take a black tile off the belly of the Orbiter and tap it with
your fingernail and that’ll chip the outer surface of the tile.
It’s very breakable, very fragile, which is why we spend a lot
of time processing and repairing tile after every flight.
They came up with this harder tile that we could put around the edges
of the openings, the ET door openings, the landing gear door openings.
Anywhere where there was a higher potential for a breach we were installing
these stronger tile. Of course the first question is well why wouldn’t
you just put the stronger tile over the whole vehicle? They weigh
more. So you increase the weight of the vehicle. You decrease the
weight of your payload. You increase the amount of fuel required to
get you on orbit. Everything is a trade.
Also because obviously going in and changing out, there’s 24,000
tiles on a vehicle, that would take a lot of time to go and change
them all out. So it made sense to do it in the areas of highest concern.
That wasn’t something that happened in completeness during the
return to flight flow. We did a majority of it then but then we continued
to upgrade and replace tiles in those areas over multiple flows. That
was a modification that continued for quite a while.
The other significant modification we were doing that wasn’t
return-to-flight-related was that Station-to-Shuttle Power Transfer
System or SSPTS which allows us to stay on orbit longer. That’s
a wiring modification basically wiring from the tip to the tail. So
it took a lot of time to do that, which was one of the reasons why
our period of time for doing this maintenance was about a year, even
before we had the return to flight modifications.
Ross-Nazzal:
Tell me about getting that phone call. Atlantis was actually supposed
to fly the return to flight, but it turns out that Discovery was able
to do it. Tell me about getting that phone call.
Stilson:
Scott Thurston had been the flow director; actually we were still
vehicle managers back then for Columbia. After the accident he eventually
became the flow director for Atlantis.
We all expected Atlantis to be the return to flight vehicle based
on the fact that normally we somewhat try to plan the Orbiters’
flights in a row. If [OV, Orbiter Vehicle]-102 [Columbia] flew then
[OV]-105 [Endeavour], [OV]-103 [Discovery], [OV]-104 [Atlantis], then
back to [OV]-102. That changes very often, but that’s how we
lay it out to begin with. Based on the fact that Atlantis was the
next vehicle that had been scheduled to fly, we all assumed that the
order would not change and therefore Atlantis would be the next one
to fly. They quickly, from a program perspective, realized that with
Discovery already being in a maintenance period and then all these
additional mods that needed to be implemented, it made sense to do
those mods on Discovery first. Then obviously that would be the first
vehicle that would be ready.
Scott was actually the one to give me the news. He was in the meeting
or on the telecon [teleconference] where they made that decision.
It was a late afternoon, and so I was already at home. He called me,
and he was the one to tell me that. Scott is a great guy. I’m
sure he was very disappointed. I’m sure he wanted it to be Atlantis,
as I would have if I was in his place. He said, “Hey looks like
you guys are up. We’re looking for you guys to pull it through
and take us back to flight.” I was very excited about that.
I was shocked, because I wasn’t expecting it, but very excited
because I knew it would be something really good for my team.
The KSC team as a whole, the NASA team as a whole—I want to
look out for all of them, but my primary function is to look out for
my Discovery team, that’s part of my job. So I was very happy
that they were going to get that, because once again it gave them
that focus of, “Okay guys, we will never forget about this accident.
But we need to focus on getting back to flying, that’s what
we do here, that’s what we need to process for.” I think
that was helpful to the team.
Ross-Nazzal:
Did you ever talk with the previous flow director for the return to
flight following [the Space Shuttle] Challenger [accident, STS 51-L]
to get a sense of what he or she might have gone through?
Stilson:
No I did not. That would have been a really good idea. To be honest
with you—I hate to admit it—I’m not even sure at
the time who that flow director was. I am guessing it was “Tip”
[John J.] Talone [Jr.]. I actually worked for Tip Talone when I worked
for the Station Program. I did not know him when he was a flow director
Unfortunately I haven’t had a lot of interaction with previous
flow directors besides the ones that were still working Shuttle when
I joined the team, like Kelvin Manning. I haven’t had much interaction
with those flow directors from the far past. We were trying to put
together a history to show all the flow directors along the way. I
hope that we’re able to pull that together, because I love the
job that I do, and I’m sure they felt the same way when they
did it. “Pepper” [Philip E.] Phillips is another one.
He was a flow director. He’s still around and was the Deputy
Director of Shuttle Processing when I was a flow director. So I’ve
worked with and for him. Grant Cates was in my office. He wasn’t
acting as a flow director then, but he had been the flow director
for 102. I had some interaction with the ones that were flow directors
just before I came on, but not many of the ones from farther back.
Ross-Nazzal:
Tell me about the media interest and really the scrutiny about what
you were doing with Discovery and making sure that every I was dotted
and T was crossed.
Stilson:
There was a lot of media attention during the return to flight timeframe,
I never thought about the media aspect of my job, but it quickly became
a big aspect of being the flow director. Fortunately I had an awesome
public affairs representative, Jessica Rye, at the time. She just
got me through it and helped me prepare and feel comfortable. Without
that I think it would have been a very unpleasurable experience just
because it was my first exposure to the media and it happened very
quickly. Jessica really helped me feel comfortable and confident.
Actually I really enjoy that aspect of my job now. I did a lot public
affairs events then and then it dwindled off. Now that I’m working
transition and retirement, it has ramped up again so it is a large
part of my job again.
In regards to the impacts of having all eyes on us, once again I pride
the team for not letting that affect them too much. I think we put
enough pressure on ourselves that any pressure from the outside was
not going to even measure up. We all were so anxious to make sure
that we were doing the right thing and doing a good job, and ensuring
that Discovery had a great mission, when we had the return to flight.
Based on the CAIB report we had —I’ll call it a “mods
on the fly” kind of scenario. Based on the CAIB’s findings
the program was developing mods. We were implementing them almost
immediately after they were developed. That was challenging. But other
than that I didn’t see any real—I’ll call it a negative
effect from the CAIB. Of course once again heightened focus on safety
on making sure that we were doing everything we could to be as safe
as possible, a huge responsibility on the team to get us back to flying.
But I, once again, didn’t feel pressure coming so much from
the outside. It was more internal to ourselves and who we are and
what we do.
I think the program did a good job of protecting us from a lot of
external pressure as well because everything that we do here at Kennedy
obviously has been approved by the program. We’re really just
the implementers. At the program level they were the ones having to
go under the scrutiny of being asked have you done enough? Have you
done the right thing? Is this all that needs to happen? The program
helped keep those questions away from us.
Ross-Nazzal:
Earlier you were talking about some of the challenges working with
JSC, where they might want to implement something but it’s going
to drastically impact schedule. Was that something that you were dealing
with with return to flight? Were there other changes that they wanted
to make to the Orbiter to ensure that the crew would be safe? And
you thought maybe this is too much or it’s too much time?
Stilson:
I think eventually we implemented everything that they felt we needed
to. I saw more of what I thought was doing too much after we got back
to flying, because we continued to obviously want to improve and do
things better. At that point is where I think we were in an overkill
mode, polishing the apple per se, as opposed to really balancing the
risk of what we were doing. Yes, there were times where I felt like
certain modifications and special tests were approved without a true
necessity for doing the work. I can’t, right off the top of
my head give an example, but I felt that there were things that we
did to the vehicle that we really didn’t need to do. It wasn’t
necessarily improving the safety. Nor was it improving the success
of the mission. Now, that’s my opinion. The people that came
up with those modifications and special tests I’m sure would
argue vehemently that I am wrong. But, that was my perspective on
things. I was anxious for the program to scrutinize some of those
new requirements more than they did.
But I also understood where the program was coming from as well, and
the pressures they were getting from the outside for ensuring that
we were doing everything that we possibly could. Like I said, it’s
a balance. [N.] Wayne Hale was in that position [Shuttle Program Manager]
because he could handle that. He’s a pay grade much higher than
mine and those decisions come with that territory.
Overall I was very impressed with the way things were handled, especially
with Wayne Hale. I got to spend six months working with him in Houston
on a rotational assignment. One of the biggest things that I learned
from Wayne, or that I respected even more once I spent more time with
him, was first of all his ability to make everyone feel important
and to feel needed and necessary. He deals with thousands of people
on a regular basis. I would walk around with him and see him take
the time to stop and talk to the person from the janitorial staff.
“Hey, how’s your day going? How are things for you? Thank
you for what you do.” Really just constantly with all these
pressures he had on his mind that he must have been dealing with to
still take the time to make sure that everybody on his team felt that
he personally needed them. I tried to learn a lot from him. I think
he did a great job.
We also saw Wayne bring out the dissenting opinion. Everybody always
knew yes, we have dissenting opinions. Wayne was very adamant about
saying “I need to hear a dissenting opinion. We’re not
going to leave this meeting until somebody gives me a dissenting opinion,
because I know there’s one out there. We need to not be afraid
to voice our dissenting opinions. We need to hear them.” I think
we needed that at the time. We were almost forced into that dissenting
opinion so that now it’s not taboo. Prior to the accident I
think there was some feeling you were going to be shunned if you brought
a dissenting opinion up in a public forum. Now it’s very commonplace
for anyone at any level to bring something up.
Now should you follow your chain of command and follow a process?
Absolutely. We’re not looking to change that. If you follow
that process and still feel uncomfortable there’s plenty of
open forums where you can stand up and talk. I think that’s
been a real positive for NASA and something that I don’t think
that we’ll get away from. I think that’s been ingrained
in us now. That has become part of our culture.
Ross-Nazzal:
What other changes were brought about by the accident? Obviously there
were new systems on the Orbiter. Were there changes in inspections
in terms of what you were doing here in the OPF?
Stilson:
Yes. The main thing that changed was the inspection process; I mentioned
the reinforced carbon-carbon panels for one. Also in the past on the
tile—I talked about the fact that you don’t always have
to change out a tile, if there’s damage. You can repair it.
One of those repairs is called a putty repair, and it’s called
that because you’re basically putting a type of putty into the
hole, smoothing it out, baking it, and then it’s usable again.
Well, we went through a process of basically getting rid of any large
putty repairs, because there was concern that they were going to come
loose and could become debris that could damage another part of the
vehicle. So that was a different mindset, because now you’re
changing the inspection criteria and then going in and removing what
in the past had been considered a perfectly good repair technique.
It still is but only for certain sizes. That was a big change not
only in the fact that from now on with new damage you may not be able
to use that putty repair anymore, but also going in and digging all
those repairs out. Or removing and replacing the tile based on the
fact that the putty repair area has become too large.
Another big change was the addition of the on-orbit inspections. That
was a huge thing for the crew and Mission Control, but from a ground
processing perspective the additional thermography and minute inspections
were the biggest impact to us. Earlier I mentioned the blankets and
the fact that, prior to the accident, we were not scrutinizing the
blankets or the whole thermal protection system as much as we are
now.
Ross-Nazzal:
Any major challenges that you faced on this flight? I think it was
your third flight. Is that correct?
Stilson:
Yes it was. I thought back about that. It was over three plus years
before we actually flew again. We spent just under 1,000 days in the
Orbiter Processing Facility. I had to go look that up because I was
wondering myself. Just under three years in the OPF. That’s
an enormous amount of time.
That OMDP was actually the first one that was being done at Kennedy,
a full OMDP. We had done partials in the past, but previously full
OMDPs were done at Palmdale [California]. So even going in, before
we even got to the Columbia accident, we were under a lot of scrutiny
because there was still a pocket of individuals that felt like that
work should stay at Palmdale, that it shouldn’t be done at Kennedy.
Even before the process began there were a lot of discussions and
us having to prove that yes we were capable of doing this work, and
that it should be done here. We discussed the costs of ferrying back
and forth to California, and how staying at KSC would avoid that cost.
We’ve got the workforce here. We’ve got everything we
need.
Once again I think we put a lot of pressure on ourselves because we
wanted to, of course, make sure we did this right, because now we’re
going to be judged on, “Ah, well, if we’d done this at
Palmdale, maybe it would have been done quicker,” or something
like that.
So that was already the challenge and then once you lay on top of
that the return to flight modifications, and not being able to operate
in as much of a controlled fashion as we were used to. The way we
had operated in the past the program would have said, “Here
are the mods, you’ve got six months to go write the procedures
for them and get the requirements defined.” All of a sudden
it was, “Okay when can you have the procedures written and get
them executed and what is that going to mean to the schedule?”
Not the best way to plan a processing flow. Nominally an OPF flow—believe
it or not—is about 40% unplanned work. That surprises a lot
of people. It really surprised me when I heard the statistic. I think
that goes to show how much the vehicle is still a developmental vehicle.
Everybody wanted to think a long time ago that this was going to be
a very routine thing like flying an airplane, and it’s really
not. That’s because every time we process a vehicle we find
something new, or the engineers come up with something, “Hey,
maybe we can improve this system, maybe we should do this differently.”
As a flow director, we go into a processing flow with a baseline schedule.
“Here’s what we have got to do.” We have built in
contingency, knowing that we’re going to have some of that unplanned
work. But you never know what it’s going to be and what that
overall impact is going to be.
If it’s something small, okay, no problem, you can absorb that.
We have built in contingency to allow that to be absorbed. If it’s
something major that drives you to go pull off an OMS [Orbital Maneuvering
System] pod then that’s a completely different activity. Then
you get into the process of, “Can we do that work in parallel
with everything else and still maintain our schedule?”
By saying that, if I go back to the return to flight flow, it was
almost as if all of those things were happening at once at a very
large scale. So opposed to having just a few little problems or modifications
to add, all of a sudden we had these huge modifications to add, where
we were waiting on hardware, because it was being developed real-time.
Then sometimes maybe that hardware didn’t look exactly how it
was supposed to. Once we got it here and tried to connect it into
the ship it didn’t fit right. Now do we send it back to modify
it or do we modify it here, because we have some skills here that
can do that.
It obviously took a lot more communication and work between Centers
than we nominally would have to do, a lot more back-and-forth. The
way we normally do it is we receive the requirements, and we implement
them. Sometimes there are issues that require us to coordinate back
and forth with the designers. During return to flight this was a constant
day-to-day, hour-by-hour back-and-forth with the requirements developers
that we didn’t normally have to do.
Ross-Nazzal:
Tell me about that communication. You’re in charge of this vehicle
but you’ve got responsibility to talk to people in Houston,
the Orbiter Project Manager, the Space Shuttle Program, the ET Project
Manager here. I’m sure there are plenty of people I can’t
even list. Talk about communication. Has that evolved over the years?
Stilson:
It has. We got to a point where we developed what I call the core
team for Discovery, and each vehicle has done that. It’s comprised
of your leadership folks from both an operational and technical side
here at Kennedy on the NASA side, then also on the USA side, as well
as Boeing. We have a Boeing vehicle manager and a USA vehicle manager.
My main counterpart is a USA flow manager and then we have integration
folks as well. There’s also a representative from the Orbiter
Project Office who is the JSC vehicle manager who is basically my
counterpart with the Orbiter Project Office. We got to a point where
we had a daily tag-up in the morning to talk high level issues, concerns,
anything of importance. That allows us first of all to sync up and
make sure everybody understands where we are with processing, what’s
going on. Then communicate especially to Houston, “Hey, we need
this from you guys. This isn’t working the way we expected.
We need you to go help us with getting the new requirement,”
or whatever it is.
So that’s really helped. Then from a higher level, I obviously
have management here that I report to. Then I also have the program
that I report to, Mike [Michael P.] Moses being our program rep [representative]
here at Kennedy is the person I have the most interaction with. For
example if there’s a new requirement that comes through, say
a special test; a chit is what we call that. It’s my responsibility
to tell Mike what the impact of that chit will be. So JSC says, “We
want you to go do this.” Then I go back to Mike and say, “Okay,
Mike, this is what it’s going to take to do it. Do you want
to approve it outside of board? Do you want to have them present you
with the details of their request and have me present the schedule
side of it?
We had a lot of that type of interaction with Mike. His involvement
gets even greater once we go integrated, because at that point in
time he’s very interested about any additional work. The later
you get in the flow, the less you want additional work that could
drive something unexpected, because any time we make a change to the
vehicle there can be negative fallout if it doesn’t go as expected.
That’s why we at Kennedy somewhat have the reputation, especially
to the folks at JSC, of not wanting to do work. We are often accused
of “saying no to everything.”
I understand why they say that, because we do. I also understand that
we have that obligation to once again push back a little bit, because
although a task may sound very simple, I go in to do it, and heaven
forbid the technician drops a wrench on top of an RCC panel. That’s
over $1 million to replace and it takes a year. Things happen. As
careful as we try to be, those are the things that we have to think
about. So I feel like we’re almost like that conscience, “Let
me remind you that although this sounds like a really good idea, we
have to remember that unless we really need to do work on the vehicle
it might be taking a risk that we as a program don’t want to
take.”
So once you’re integrated, of course, that risk goes up by three
now, because when you do something on the Orbiter you could impact
the boosters or the tank, or vice versa. You increase that risk. So
Mike at that point becomes very interested and is not willing to take
as much risk. In the OPF I can approve special tests on my own. If
it’s not a big impact to the schedule I can say, “No we’re
good to do this; we’ll just take it on.” I won’t
have to bother Mike with it. Once we go integrated, he wants to be
bothered, even if it’s something that I think is going to be
a simple task and not take much of our resources or our time to do.
Ross-Nazzal:
How closely was the RTF [Return to Flight] crew following what you
were doing here at Kennedy?
Stilson:
They were here I believe as much as they could be. Their training
schedules I know are horrendous. They paid several visits to the workforce.
I think for a couple reasons. I know they’re interested in seeing
what we’re doing. Obviously they have a very big interest in
that. So they were here in that respect. Even more importantly they
were here to encourage the team and show they appreciated what we
were doing, because that was a very hard time for us. It was a lot
of work. We were working around the clock because everybody was so
anxious to get done. We weren’t overworking people. We have
workforce rules that we abide by to ensure that we’re not overextending
anyone. Still being an environment that’s used to launching
Space Shuttles and going that long without a launch, it weighs on
folks here more than anywhere else.
Plus there was that unknown of will we ever really fly again. That
even crossed my mind in some of those cases. A lot of the reason why
it crossed my mind was going back to that “polish the apple”
scenario. “If we don’t draw the line somewhere we’re
never going to launch again, guys. We have to get moving.” Although
nobody talked about it much there was still in the back of everybody’s
mind, “Are we done; is the Space Shuttle Program done because
of this accident?”
That’s what made the actual liftoff of that mission so critical,
well maybe not the liftoff as much as the landing. I think that was
even bigger. The liftoff was great. Launch is always a great day,
and we were excited because it was the culmination of our work. But
to really prove that we had found the problem, fixed it and could
fly again safely, we needed to land. So landing day was really more
of a relief, I think, for the Kennedy team. “Whew, we did it.
It really happened. We really got through this. We’re back to
where we should be.”
Ross-Nazzal:
Were you the person who signed off that said, “Discovery is
ready to go when she leaves the OPF?”
Stilson:
The process that we take, there’s reviews all along the way.
So the first review of that kind for me is the Orbiter mate review.
Actually let me step back.
We have an ET mate review. So before we mate the tank to the boosters
we have a mate review to ensure that we’re okay there. If there
were any technical issues along the way we talk about what they were
and how we fixed them. Or if there’s still open work, we discuss
when we’re going to do that work and how we’re still going
to be able to mate on time. Or we need to move the mate date. That’s
the first one. That one is usually pretty benign. There are usually
not a lot of issues with mating the tank.
The next one being what we call the Orbiter mate review. That’s
where we talk about what’s been done on the Orbiter and that
we’re ready to roll from the OPF over to the Vehicle Assembly
Building. Once again high level we talk about the work that was completed,
any technical issues along the way. I don’t sign-off for that
review. I’m presenting data so that others feel comfortable
to sign.
So now we’ve had these two mate reviews and we continue processing.
The next big review that I’m involved with would be the launch
readiness review. That is where I stand up and give a highlight of
the flow for the Orbiter, boosters, and tank. I describe the challenges
we’ve had and detail the remaining work in front of us. I discuss
the contingency remaining and give my position on the likelihood of
meeting the target launch date. When my part is complete the Orbiter
Project engineer talks through any technical issues of interest.
After the launch readiness review then we get into the flight readiness
review, which bumps up above me. Although I prepare the charts that
the launch director uses, it’s the launch director speaking
for us at that point in time to say yes we are ready. So if I think
about it, the only review that I actually sign off on myself is our
internal launch readiness review. The external one to the program,
my director for launch vehicle processing, she signs that based on
what I’ve given her as information about where we are and how
things are going.
Ross-Nazzal:
Are you in Launch Control the days before mission and for liftoff?
Stilson:
Yes. Actually we have the Shuttle test directors that run countdown.
They basically lead the launch team. Although there are members of
my ground processing team that are also members of the launch team,
it’s somewhat as if I’m handing control over to the Shuttle
test director. I’ve done my part. I’ve got the vehicle
ready to go into countdown. Now the Shuttle test director has to finish
the job, get us through countdown and liftoff.
During the four days of countdown, I’m not in the firing room
until launch day. There’s really not a function for me during
a nominal countdown. If something goes wrong, then I am back in the
mix of things and depending on the problem I can potentially step
back into the leadership role. It’s a real close coordination
between the Shuttle test director and myself, because if we have a
vehicle problem then that immediately goes back to my responsibility
of fixing it so we work very closely together through that process.
Then on launch day I’m in the firing room. The flow director
doesn’t have an active role with the launch team, which means
we don’t have a call on the net where we say we’re good
to go or anything like that. We do sit on console with the launch
director and the assistant launch director and help them with anything
we can help them with. One of the most helpful things we can do is
assist with monitoring voice loops. In addition if there are targets
of engagement, aircraft in the controlled area, the flow director
will help plot their location. Basically if the assistant launch director
is the launch director’s right-hand man; the flow director is
the left-hand man to pick up anything else that has to be done.
We are there more in the sense that we’re the only person that
has followed the processing flow the whole way through. We are the
consistent factor for that vehicle. So the launch director, assistant
launch director, they do all the launches, but they’re not part
of all the ground processing to get us there. If there is an issue
that comes up, they’re going to look to me to say, “Is
this something we saw in the OPF? Is it something you’re familiar
with, or is it something brand-new?” So it’s a consistency
role and a reward for being the leader of the team that has gotten
us this far along.
Ross-Nazzal:
Tell me about the landing. You said that that was probably the most
memorable moment. You were out in the Shuttle Landing Facility [SLF].
Tell me about that.
Stilson:
It was great. I’ve gotten to be at the SLF for every Discovery
landing that I’ve been a part of. It’s so quick. It’s
like you’re waiting, you’re waiting, you’re waiting.
All of a sudden it’s there and then it’s landing. It’s
hard for me to describe if someone’s not seen one. You’re
looking; you’re looking. Sometimes you can see it way overhead.
When it’s coming down it just seems to almost fall out of the
sky and then it’s on the ground. Obviously for return to flight,
a lot of us were just very anxious to land. Prior to the deorbit burn
we are in the firing room awaiting the “Go for landing.”
We’re listening to the voice loops and watching Mission Control
on the television monitor. On STS-114’s landing day it was decided
that we were going to land out west so we weren’t real happy
about that because we were anxious for it to land at Kennedy. But
that decision is made from Mission Control so we don’t have
any say in the matter. The reaction for the return to flight landing
probably wasn’t as impactful because it didn’t happen
here as it would have been. Still hearing they had touchdown, that
was all great. Then we immediately head out to California and start
processing for the next mission.
We leave for California the day after landing. Watch touchdown on
TV from the firing room and then go home, pack, and get ready to leave.
We usually plan to be out there two weeks just in case, but it usually
only takes about a week to get the Orbiter ready to ferry back. Flow
directors are part of the ferry flight back as well. We lead the team
that’s out there processing, getting it ready to ferry back,
and then we’re on the Pathfinder on the way back. Based on weather
the ferry flight could end up taking a week to get back so you’re
never really sure when you will get home.
That’s the downside of being out there, from a personal life
perspective. You can’t say how long you’re going to be
there. It’s like, “Well our schedule says we’re
going to be ready on this day but then we’ve got the ferry so
maybe in a week we’ll be home.” We never want to land
out west because of the risk of ferrying the vehicle cross-country.
There’s a lot of risk involved with that. Plus the additional
time that it takes out of our processing schedule because we know
there’s always a chance to land out west, so we build in some
contingency based on that. But we’d always like to have those
days. If we can have those extra days for processing at KSC that would
be great.
It’s very costly, I should say that too. It’s obviously
costly to ferry the vehicle so we don’t want to spend money
that we don’t have to spend. The fun part of being out there
is it is even more focused than we are here in the sense of we’re
all out there to get this job done and get home. It’s nice to
have a little more close relationship with that smaller team while
you’re out there than we have here, because here you still have
your distractions of your home life and things like that, where out
there it’s like night and day this is what we’re doing
until we’re ready to go.
It’s enjoyable being out there. The folks that work out there
full-time of course love it. It’s nice for them to get a chance
to process the vehicle, because they’re out there prepared and
ready to go every time. We send people out as well. We actually have
folks that go out there a couple days before launch, and they stay
out there until landing because they’re required to be there
in case we have an emergency landing. So they’re already out
there, waiting. I can imagine how they feel, because they go out every
time, and they have to get everything ready to go, and then it doesn’t
land there. That’s probably a little bit frustrating for them
as well. I’ve only had two opportunities with Discovery landing
out west. They’ve been good experiences though.
Ross-Nazzal:
How many people end up going out there?
Stilson:
There is a small group that goes out prior to launch. Then a couple
of days before landing we send the first wave which I believe is approximately
45 people. Then we send about 60 more the day after landing. So over
100 folks are required since we’re operating around the clock.
We have to cover three shifts a day when we’re out there.
Ross-Nazzal:
What do you have to do to get the vehicle ready for ferry?
Stilson:
There’s some initial safing that we do, cryogenics and so forth.
There are some things, mostly payload items that have to be removed
from the forward—the middeck area, just like we would do here.
The main thing is getting it to a position where we can lift it up
and get the 747 underneath and mated so we can ferry home. There are
some SCAPE [Self-Contained Atmosphere Protective Ensemble] operations
which are hazardous. Initial draining and safing of the systems that
contain hazardous commodities such as cryogenics, hypergols and ammonia.
We’re also looking for any type of leaks. If we have anything
like that we have to take care of it before we can ferry.
We have to put plugs into the water spray boiler and auxiliary power
systems. Also we have to do inspections for the thermal protection
system. Not only do we have thermal protection system requirements
for launch and for the mission, but for ferry we have requirements
to ensure we don’t have any billowing blankets or things that
as we’re flying cross-country would rip those blankets off or
do damage. It’s a smaller team, but there are quite a few systems
that are involved. For example, hydraulics engineers are required
because we have to retract the landing gear once we lift up the Orbiter
to mate it on the 747. They have to retract the gear and make sure
the landing gear are properly closed out.
Ross-Nazzal:
How did Discovery look when you got out to see her?
Stilson:
That one, I don’t remember there being anything that wasn’t
typical in regards to the tile damage. I expect I looked at it and
said, “Wow this looks great. Obviously all these mods to the
tanks and things have done well,” but then when we got back
to the OPF and they did the minute inspections, we had many repairs
to do. I thought, “Wait a minute, it looked so clean.”
So that’s been a running joke, because every time we have looked
at Discovery on the runway since then we’ve always thought,
“Gosh this looks really good, I don’t think we’re
going to have much tile work.” Then we end up with just as much
if not more, because our eyes are not trained to look for what the
experts are looking for.
The same thing happened after STS-133. That was a unique situation,
because normally when I’m looking at Discovery after a mission
I’m automatically thinking, “What is this going to mean
for processing? What additional work are we going to have to do? What
is this going to mean to the schedule? What’s the impact of
what I’m seeing?”
Several times I had to shake my head and say, “Oh you don’t
have to worry about that this time,” because we’re not
doing a lot of tile repair before we ferry it to the Smithsonian.
I had to keep reminding myself to just enjoy what you’re looking
at. Once again it looked beautiful. I was very impressed. I said I
thought it was the cleanest I had ever seen it.
We were really struggling to find any kind of tile damage. There just
really wasn’t any. Normally there are a couple somewhat significant
gouges that are obviously from ice off the tank or some foam, but
never anything that I was ever worried about. These were just turnaround
issues we had to fix before the next flight. But after STS-133 the
damage was very minimal.
It made me a little bit angry because it was so clean, not because
I wanted to see damage but because it made me think, “Why are
we not continuing to fly these vehicles?” We feel like we’ve
really gotten a handle on the things that we needed to improve, and
as soon as we do it’s the end of the program. So a little bit
of negative feeling there, but overall I’ve stayed very positive
in that regard. I think I deal very well with change. It’s not
a decision I could affect. The decision was made. Therefore we’ve
got to act on that decision.
It also helps that I’m getting to work transition and retirement.
So I’m going to be able to work on all three of the vehicles
right up until we deliver them. My team will be the team that actually
delivers those vehicles to the display site. I’m very fortunate
to have that opportunity, and it’s been very exciting work so
far. So I’m very fortunate for that.
Ross-Nazzal:
Any other memorable missions besides 133 and return to flight?
Stilson:
Yes. Return to flight actually, that stands out the most obviously
because of everything involved with that—the amount of work
that it required and the attention, and the media side of it. As I
thought back over some flights, STS-116 was actually the shortest
OPF flow since return to flight. It is still the shortest flow. It
was a very intense time getting through that flow but also it was
very rewarding. We’re like anybody else that works in a team
environment; we have some competitiveness amongst the different teams.
To be able to say, “Hey we processed Discovery in the shortest
time since return to flight,” that was a big deal for the team.
When we roll out of the OPF—there’s always celebration
involved with meeting a major milestone. That’s the first major
milestone once you start a processing flow. Major milestones being:
rolling out of the OPF, then rolling out to the launch pad, and then
launch. So with that being the first major milestone, everybody was
really excited about it. That was memorable.
Then STS-128 was a relatively quick OPF flow, not the shortest, of
course, but quick. The real challenges for that flow happened after
we went integrated. It ended up being a zero contingency flow. We
normally go into an integrated flow with at least five days’
contingency, at an absolute minimum three, but there have been some
that we’ve had zero contingency based on trying to get to a
launch date and other factors that are affecting that launch date.
In the case of STS-128 there was a window of time right after our
target launch date where the range was not going to be available to
us and then there were other constraints such as beta angle cutouts.
It was a situation where if we didn’t make the targeted launch
date the next attempt wasn’t going to happen right away. A delay
of that magnitude was going to have a ripple effect through the rest
of the flows.
We did not, as the people responsible for preparing these vehicles,
want to be the reason that we missed the target date. That’s
our job, to be prepared and be on time. Not to say that if something
happens that makes us feel like we can’t get there that we wouldn’t
speak up. If it comes to that then I’m going to be the first
one to say, “John [P. Shannon, Space Shuttle Program Manager],
we can’t do it; we can’t get there.”
We had some technical issues during that integrated flow that were
very challenging, things that we had not had to deal with previously.
Each time a problem arises I work with my USA counterpart for the
integrated flow, which is James [G.] Taylor to resolve it. We determine
the impact, and then what that impact means to everything else in
the flow. So we basically build schedules to show what would change.
In each case that we had an issue come up, we were able to lay a schedule
out that showed, at least on paper, that we could still maintain our
launch date.
Understanding that the schedule is only as good as your guess on how
long it takes to do the work. For the guys executing, we talk to them.
“Hey, how long do you think it’s going to take to do this?”
That’s what we’ll use. We’ll go from there. Now
granted, engineers versus operations people don’t always agree
on times so we had some good discussions along the way. But the questions
JT and I have to answer are, “Do we really think that we need
to come off the launch date now? It sounds like we still have a chance
to make it. If we do, why wouldn’t we try? Why wouldn’t
we try to get there?” JT is a little more conservative than
I am in regards to that. Granted, he’s the contractor so he
probably feels that he’s going to be assessed more with that
answer than I will be.
For STS-128 we discussed it and said “No, we can’t in
good faith say we really have to come off the launch date yet.”
Now can something happen tomorrow that drives us off of it? Sure.
So the way that we looked at it was if it’s important for us
to get to this launch date, and we still feel like we have a chance,
then we should try. No guarantees, but we should try.
So that’s what we did. Lo and behold, we got through some challenges,
and we were able to make the launch date, which was a great thing.
Afterwards there was some fallout in the sense that some folks felt
that we pushed too hard to get there and that’s where you get
back into that schedule pressure discussion. We had a lot of lessons
learned on how we communicate, and what the team’s perceptions
are, whether their perception is really what’s happening or
not. If that’s their perception, that’s real to them so
we need to make sure that their perception is accurate. If it is not
accurate then we need to clarify and discuss with them. So I’ll
say I took some heat for that. I did some self-assessment in regards
to the way I communicated with the team and what I could have done
differently. I would not have changed my recommendation to continue
working towards the target launch date but I would have looked and
listened harder for those perceptions. I think that we did the right
thing, but you can always learn from any experience. Some people felt
a bit uncomfortable with the level that we were operating at, and
we did make some changes after that. We decided, “From now on
we’re not going to go into a flow with zero contingency.”
That’s really not a smart thing to do. You really shouldn’t
because it does create pressure. The contingency days are there for
a purpose, and that is to allow that if you have some stumbling along
the way you’re not immediately impacting a major milestone.
Nobody on the Space Center ever wants to have to impact the launch
date. They’re all as anxious to launch as anybody in the program
is. So when you have those contingency days it definitely gives a
little bit of relief to the team. We strategically put those contingency
days after major operations, where we have a higher likelihood of
encountering problems. We’ve gotten very good at where we stage
those contingency days. I definitely took a lot of lessons out of
STS-128, but overall I was very happy with the results and proud of
the way the team executed.
The only other flow I’d mention would be STS-133, which we talked
about already. Not just because it was the last one, but because of
everything it took for us to get there. On launch day, we had the
issue with the range. I don’t know how much you heard about
that or followed that. We thought we were going to have to scrub for
a range issue. For an issue that we were hearing was fixed, but we
couldn’t get them to say on the loop that it was fixed. I’ve
had people say they saw me on TV while that was happening, and they
could tell how frustrated I was.
I’m not very emotional. I am a very emotional person but I don’t
usually show that. Unless you know me very well you don’t know
that I’m an emotional person. I have somewhat of a rough exterior.
So everybody kept saying, “Are you going to cry on launch day?
It’s the last one, you’re going to cry.” I really
didn’t feel like I would, because I knew I was working transition
and retirement. So really my job with Discovery wasn’t done.
I felt I’d be more emotional when I take Discovery to the Smithsonian
and then I leave her there. I think that’s when it’ll
be an emotional hit for me.
On launch day of course I was thinking, “Am I going to feel
emotional?” I wasn’t sure how I’d feel. When we
had five minutes left in the count, I was starting to feel a little
emotional and then when we had the snag, and I thought we were not
going to launch. Prior to that point, the launch director kept saying,
“Nah, we’re going to go today. They’re going to
get this resolved; we’re going to go.” Mike’s words
assured me it was going to be alright.
Well then it got to a point where Mike said, “I don’t
know, Steph. I’m getting worried now,” because he didn’t
think they were going to get the issue resolved. I literally at that
point started to tear up, because I thought to myself, “Don’t
put this team through this. They have worked so hard to get to this
launch. Weather is perfect. The vehicle is perfect. This is something
completely out of their control. Don’t do this to them.”
I could feel it in the firing room, everybody was thinking, “Oh
my gosh, please don’t tell me we’re going to scrub a launch
for something like this.”
I had to get control of myself. Then once we got the go, oh, I was
so relieved! Obviously my emotions showed through to people that were
watching on TV, because I was getting very aggravated. I was literally
thinking about everything that the team had overcome to get us to
that point and then to have it taken out of our hands like that was
going to be awful.
To have to start again that’s such a letdown. Any time you have
a scrub, no matter what the cause, it’s a huge letdown, especially
if now you’ve got to go do a bunch of work, like we did with
the tank on the first scrub. My initial thought was, “Oh my
gosh, now what do we do and how long is it going to take?” So
thank goodness we got STS-133 off on the second try. The range came
through for us in the end.
Ross-Nazzal:
Tell me about how processing has changed over the past ten years.
Are there significant changes or just minor differences?
Stilson:
I think the main change that I’ve seen –we touched on
it a little bit at the beginning— was that we’ve become
more of a unified team, NASA-contractor team. That’s so important.
It can be hard, because obviously as NASA it’s our responsibility
to critique what the contractor does and to ensure that they’re
doing the right thing.
Of course we have to think about cost and schedule as well. If they
don’t do something correctly, we have to write them up and that
goes into their award fee. That can potentially affect their salaries.
So we work so closely together. We’re very much a family. Then
to have to also score them that makes it difficult. I’ve really
seen over the past 11 years us come to a point where there’s
better understanding of that aspect of our role and how we’re
not going to use that to beat them up. Award fee is a necessary thing
we have to do. We all know it’s there. We’re going to
do our best to make sure the contractor is successful, because if
we’re going to be successful they have to be successful too.
So we want to help them be successful. Then they do stumble, depending
on what it is, we’re going to be right there with them. If the
contractor makes a mistake, misses a step in a procedure, we’re
going to have to take that forward. Then we’re going to work
with them to figure out how to keep that from happening again.
I’ve seen the communication open up to where—in the past
it would be very hard to ever get USA to share any information, much
less share something that didn’t go the way they expected it
to. Now if something happens, I know I’ll get a call immediately.
“Hey, Steph, here’s what happened. Here’s what we’re
doing.” They will also already be in the process of investigating
and doing those things they know I’m going to ask them to do.
So it’s like there’s been an acceptance of this is the
way we operate. They know what I’m going to ask. They know I
expect a lot. They know that I’m going to be looking for answers
if something doesn’t go right, but they also know that I respect
what they do. If they explain to me and just give me the information
I’m looking for, it’s going to be okay, and we’re
going to work through it together. I’m going to stand up and
take an arrow if I have to, because I’m a part of the team.
It’s not us against them. So that’s been probably the
biggest thing that I’ve seen that’s changed.
From a process perspective, we are constantly making changes to improve
our processes. So I don’t think there is any one thing I can
point out. That improvement has stayed consistent. We are constantly
asking, “How can we do this better?” Lessons learned are
critical. We have lessons learned discussions after every major task.
If something does go wrong we have a process to evaluate the situation.
We determine how to fix it and how to ensure it doesn’t happen
again. I’ve seen us continue to improve that process. Another
process improvement is the increased focus on dissenting opinions
which we already talked about.
Then lastly, John Shannon always says “Stay hungry.” Mostly
he’s talking to the engineering community in the sense of asking
are there things that we need to do to make the vehicle safer. We
at Kennedy—we’re a part of that process, because we have
expert engineers that are very knowledgeable about their systems.
And then from an operational side I see us constantly looking for
ways we can do things better. Be more efficient. Be safer with what
we do. Be more proactive about things. That’s something that
I hope that we continue to do. I’ve felt that it has progressed
over time, at least the time that I’ve been here.
Ross-Nazzal:
You had previously mentioned there was some competition between the
teams. Can you talk about your relationship and your work with the
other Orbiter flow directors and other teams?
Stilson:
Sure. The flow directors, we of course have interaction. The main
thing that we want to ensure that we do is if there’s something
that happens on Discovery that could potentially affect the other
two vehicles, it’s my responsibility to make sure they know
about it right away. So that’s something that we do. If one
of the other flow directors is in a meeting and a topic related to
Discovery comes up, they’ll make sure I know about it and vice
versa. There’s good close-knit communication in that regard.
We have to be tied together closely because of sharing resources,
and the fact that when we’re processing three vehicles, anything
one person does on one vehicle can ultimately affect the other two
vehicles. So there has to be coordination. Now do we always agree?
No. Especially with Dana [M. Hutcherson, flow manager for Endeavour]
and Angie [Angela J. Brewer, flow manager for Atlantis], I almost
feel like we’re like siblings in the sense that you don’t
always get along with your sibling. You can be completely different.
We are, all three of us are completely different in our styles and
in the way that we manage our teams.
But in the end you’re always going to look out for your sibling.
You’re always going to be there for them when they need you
and get their back. So to me that’s the way our relationship
is. Like I said very different styles, not that one style is better
than the other. I could never use the style that Angie uses, because
we’re very different in how we approach leadership and what
we do, and what our talents are.
So she leverages what her strong points are to function the way she
does, and I leverage my strong points. Dana, I think, is in the middle.
I’m more off-scale high in the sense of I’m a type A,
very much get the job done. We’re here to do a job. I think
Angie is more on the emotional side of, “This is the team, and
we need to take care of our team.” I don’t remember what
letter that is, but she’s that type more of the emotional side
of things.
Then Dana is in the middle. She can tip the scale my way or she can
go more towards the emotional side. So she’s probably the most
balanced, in my opinion, in how she operates with her team. I like
that we are all so different, because it allows me to learn from them.
I’ll never operate exactly like either of them do, but there
are certain things I can take and say, “Ah, I can use that,
I can put that in my toolbox and really learn from that.”
I think the style of the flow director really permeates through the
team and influences the way the teams operate. We all do the same
function, but how we get there is different depending on the team.
From a workforce perspective we even interchange team members. You
have your core team which pretty much stays with a vehicle. But the
technicians, safety representatives, and quality inspectors, they
move between vehicles. So you have that continuity to keep us from
being very separate teams.
The way we’re set up is the engineers and operations folks are
tied to a tail number, tied to OV-103 Discovery or OV-105 Endeavour
or OV-104 Atlantis. The technician workforce and the quality and safety
personnel are tied to a bay. Once again they can move, but there are
technicians that are assigned to OPF-2, OPF-1, OPF-3. When we had
four vehicles and three Orbiter Processing Facilities, the vehicles
were constantly rotating between those Orbiter Processing Facilities,
so the technicians didn’t become as attached to a vehicle, as
much as the engineering and operations teams.
After we lost Columbia we had three OPFs and three vehicles. Discovery
was already in OPF-3 and pretty much stayed there for the remainder
of the program. And then Atlantis and Endeavour stayed in OPF-1 and
2. At that point we had more of a dedicated full team to an Orbiter.
That environment built up a little more of that, “Hey this is
my Orbiter,” as opposed to, “This is my bay.”
They still worked multiple vehicles but I think anybody you talk to
will claim one Orbiter as theirs based on which one they worked on
the most. It became a little more of individual teams as opposed to
crossing amongst them. For instance, having the shortest Orbiter Processing
Facility flow was something that the team really wanted to do. They
wanted to say, “Hey our team did this over in OPF-3.”
If something doesn’t go well, like for instance—and I
hate to say it because it was Discovery—we had an instance where
we were towing Discovery back into OPF-3. Because we had changed a
process—we thought we had enhanced a process for the towing
operations and the spotting operations. We ended up not being able
to get spotted. We had to back up and try again, back up, try again.
We ended up doing it 11 times before we got correctly spotted.
So of course we got teased a great deal by the other teams. “Oh
can’t you guys get spotted? What’s going on? Don’t
you want to start your flow?” Once again nothing’s ever
mean-spirited, but there is that competition of wanting your team
to be the best and be seen as the best.
Ross-Nazzal:
Let’s turn to the transition efforts. We’ve got a few
minutes here. You’re currently preparing OV-103. I did see her
yesterday go over to the VAB. Tell me what’s been happening
with the Orbiter.
Stilson:
As the transition and retirement flow director for the Orbiters, I
will oversee all the safing activities and the preparations for getting
those vehicles ready to ferry or to tow over to their display site.
I will also be leading the team that does the offload from the 747
at the display sites. We turn over responsibility and ownership of
the vehicles after we offload from the 747 and place the Orbiter on
the ground. At that point, the display sites are responsible. We won’t
have much involvement after that. However, we are working with the
display sites to help them, to give them our knowledge of the best
way for them to handle the vehicles once they have ownership. But
our true responsibilities will end once we demate the Orbiters.
Discovery right after landing rolled into OPF-2, and started what
we call down mission processing. Down Mission Processing is the same
no matter whether you’re going to fly again or not. We always
go through down mission processing. Basically it’s the initial
safing, gaining access to the vehicle, starting the processing flow.
That has happened on Discovery. The difference is we also pulled some
of the safing activities into the Down Mission Processing timeframe.
The portions that we pulled in were removal of the forward reaction
control system [FRCS] and the OMS pods. We performed these tasks as
soon as we could because processing of the FRCS and OMS pods is the
critical path for getting all three of the vehicles ready to go to
the display sites.
The reason for that is those are the most hazardous systems on the
vehicle. So here’s our new goal. We’ve been processing
these Orbiters to fly in space. Now we’re processing them to
be safe to the general public. There are hypergols, cryogenics, ammonia,
Freon, pyrotechnics, all of which are systems that we have to get
into a configuration so that they no longer have any of that hazardous
commodity. Other commodities, like hydraulic fluid, are not truly
hazardous, but we’ll drain down to the lowest possible level
to decrease the likelihood of having any leaks while on display.
For processing of the OMS pods and the forward reaction control system,
we have a separate Hypergolic Maintenance Facility [HMF] here at KSC.
So we removed those modules from the Orbiter and took them to the
HMF. One reason for this is that a lot of the work just can’t
be done in the OPF. The facility is just not set up to do it. Also,
the safing of the pods and FRCS is a hazardous operation requiring
technicians to wear a full body breathing suit. Only those specially
trained personnel involved with that task can be in the bay during
the operation. All other work is put on hold.
Once at the HMF we did the initial draining and deservicing and then
shipped those modules off to the White Sands Test Facility [WSTF,
New Mexico]. White Sands is where Discovery’s modules are right
now. WSTF personnel are doing the full decommissioning, which means
they’re completely draining the systems, cutting out lines,
cutting out tanks, removing or cleaning anything that has any hypergol
residue on it. Once complete the decontaminated modules will be sent
back to us to be reinstalled on Discovery. From the outside it’ll
look exactly as if it was on the runway after its last launch, but
inside it’ll be pretty much gutted. That will allow it to be
safe to be displayed in public.
In the meantime we’ll continue to safe the rest of the vehicle
and then also do the display preparations. Meaning, for instance,
we pull out the potty and the galley every time we start a new processing
flow. They reservice them in Houston and then send them back to us
and we reinstall. Well, the display sites will have the choice of
having us put those reserviced systems back in or leave them stand-alone
so they can be shown to the public. The public will not have access
to the inside of the Orbiters once they are on display. So there will
be some things that the display sites choose to keep out of the vehicle.
The Smithsonian wants to keep Discovery as flightlike as possible
because it is the vehicle of record. So they want most everything
reinstalled when possible. They can’t have everything because
there are some things that as an engineering community NASA wants
to keep. There are a couple reasons for this. One is potential reuse
of the hardware. A good example of this is the main engines. We think
that we’ll have use for those main engines in the future. So
instead of reinstalling flight engines on the vehicles we’re
going to go with what we call a replica Shuttle main engine. It’s
a real nozzle, a nozzle that has flown before or was used in testing.
But it is what we call on a nozzle on a stick. It doesn’t have
the turbopump and all those things that makes the SSMEs so special.
The powerhead is not there.
From the outside you will see the nozzles. It will look like a real
SSME. But if you were to look into the aft of the vehicle, it’s
going to look very different because of the powerhead being replaced
by an adapter. So even though Smithsonian would love to have the flight
engines installed, they’re not going to be able to because we’re
going to reuse them.
The other rationale for keeping some things is for testing. This is
hardware that has flown in space. In Discovery’s case 39 flights
for some components that have never been changed out. So we want to
do some research—I call it science projects—with avionics
boxes, valves, wiring, and so forth. So basically engineering came
up with this wish list of, “Here’s all these things we’d
really like to have,” and then the program reviewed it. Based
on cost and schedule the program agreed to keep some components.
So we still have that type of work to do with Discovery. In the meantime
Endeavour has landed. It’s in an OPF, and it’s still in
its down mission processing phase. We have removed the forward reaction
control system and it is down at the HMF being processed. We’re
getting close to being ready to pull the OMS pods. That’ll happen
at the end of the month. We actually have a hazardous operation which
we call a SCAPE job this weekend to do cross-feed drains, which allows
us to be in a configuration to remove the pods. That’s not something
we would do in a nominal processing flow unless we discovered a problem
with one of the OMS pods.
So we have been processing Endeavour and Discovery at the same time.
Well, you saw us roll Discovery out of the OPF. The reason for that
is when Atlantis lands we’ve got to get it into an OPF right
away, because it’s got to immediately go into its down mission
processing. There are certain aspects of down mission processing that
have to happen right away, so we had to make room for Atlantis. We’re
no longer using OPF-3. We turned that over to the Center to be used
for a future customer and we’re in the process of decommissioning
it. We’ll be done with that work at the end of this month, and
then a new customer will take it over. I don’t have details
as to who that new customer is, but we evaluated releasing OPF-3 and
got approval from the Space Shuttle Program to process the decommissioning
of the Orbiters through two OPF bays. We’re just going to have
to have one sitting in the Vehicle Assembly Building until Discovery
leaves for Washington DC.
As soon as we can finish the upfront work on Endeavour, being the
pods and the FRCS, since that’s critical path, we’ll back
out Endeavour, bring Discovery into Bay 1, and then let Endeavour
sit in the VAB for a while. Discovery will be the first one to ferry
out of here, because Smithsonian is basically ready to get it as soon
as we can get it to them.
It’ll be somewhat of a shell game moving vehicles around based
on priorities. I also have the new challenge of dealing with contracts,
which I mentioned in the beginning. I’ve never had to worry
about contracts or budget. We’re still in negotiations with
United Space Alliance on what it’s going to take to do this
work. So that’s the other half of my job, evaluating contracts
and the proposals from USA. We give our government estimate, and then
procurement takes it from there. USA proposed more than we as the
government think they need to complete the job, so the negotiation
phase is in progress now to get us to a point where we both agree
on the amount of money required.
The other hard thing about the current situation is we just don’t
have a lot of money. This isn’t a situation where we can say,
“Okay however much it costs we’ll have the money.”
No. Here’s this bucket of money that we have, so we have got
to figure out a way to make it work. The size of the workforce will
go down. It’ll take about just under ten months to get Discovery
ready.
That’s a good baseline for the other vehicles. So unless I have
additional requirements, or unless we can’t resolve the contract
issue and we get delayed, it’ll take each one about ten months
of work to be ready to leave KSC.
Although we are processing three vehicles, I only have one team. It’s
going to be one very small team to cover all three Orbiters. So the
challenge for me then as the flow director is basically moving that
team from vehicle to vehicle depending on what the priority is. Right
now the priority is Endeavour so that’s where the team is focusing.
As soon as Atlantis lands, Atlantis is the priority. Will I still
have some work I can do on Endeavour? Yes, but the majority of the
people will be on Atlantis. Then we bring Discovery back. Once we
get through down mission processing on Atlantis then I can focus everybody
back on Discovery. It’ll be a constant moving of resources.
Besides just the vehicles, that same workforce is going to be responsible
for decommissioning facilities as well.
For example, I will also have to share resources to decommission Pad
A. We’re done using Pad A so it’s important that we get
it off our books as soon as we can. It’s going to be a new situation
for those of us that have been working the Shuttle Program and only
had to worry about processing vehicles.
To be clear, my primary focus is the vehicles. There are other people
looking at facilities, but now I’m going to have to go lobby
in some cases to make sure I’m getting the resources I need
for the vehicles. Because it could turn out that based on cost it
makes more sense to shut down Pad A as soon as possible so then you
might want to move everybody over there. Well, what does that then
do to the vehicle schedule? Does that hurt me or is that okay based
on when the display sites are ready to take the vehicles? A lot of
coordination will be required. It’s been great. I’ve really
enjoyed it already. Dealing with the display sites, we’ve had
some site visits, talking with them.
They’re so excited to get the vehicles. Granted there are a
lot of people that were very disappointed that they didn’t get
a vehicle. I can completely understand that. Once again, this is something
beyond our control, so we’ll just deal with it and go do the
best job that we can. It’s a complicated operation, the offload
of the vehicles once we get them to the display sites. It’s
about 30 days of work with probably about 45 people. We’re still
negotiating how the work is going to lay out. Thirty days to get everything
there and set up. We have this big wind restraint system that connects
to the Orbiter. We will have two heavy-lift cranes holding on to a
sling lifting up the Orbiter. If there are strong winds it’s
like a sail. It can catch the wind, and prevent us from being able
perform the off-load.
To mitigate this we have the wind restraint system that is made up
of four masts with taglines that connect to the sling. The system
controls the lateral movement while we’re lifting the Orbiter
up, moving the 747 out, and then setting the Orbiter down on the ground.
Ross-Nazzal:
So you’re not going to be using the mate/demate device.
Stilson:
We will use it here to onload, but we won’t have one at the
display site. So you’re exactly right. The wind restraint system
takes the place of the mate/demate device. It’s actually a system
that was designed to be used at TAL [Transatlantic Landing] sites.
If we ever landed somewhere where we didn’t have a mate/demate
device, that’s how we would have offloaded. Fortunately we’ve
never had that happen. So we actually just did a dry run recently
to make sure we knew how to properly operate the equipment. This stuff
hadn’t been out of boxes since we used it in ’85 when
we took Enterprise to Smithsonian. That was the last time we used
it. Before that it was used when they were offloading Enterprise in
Mobile, Alabama, for the World’s Fair. That was ’84 I
think.
Yes, all this equipment has been in a box. Procedures have been on
the shelf. We’ve been going through the process of dusting them
off. We set it all up out at the SLF and made sure we understood how
it works. We are still updating procedures and improving hardware.
Neat work.
Ross-Nazzal:
Cool job.
Stilson:
Yes, I’m very fortunate.
Ross-Nazzal:
We have just a few minutes. Anything else that you want to add? As
we talked we really hit on most of the questions that I had thought
about.
Stilson:
I think the only other thing—you had asked me about being in
the Launch Control Center and then maybe Mission Control during the
missions. I wanted to tell you a little bit about that. For a flow
director, on-orbit time is really our only down time when you think
about it, because at that point we’ve handed control over to
Houston. At that point all we are doing is preparing for the vehicle
to come back and start over again. So that approximately two-week
timeframe for me is usually when I take some time off.
We do have the opportunity—I know Angie Brewer who’s the
Atlantis flow director is there now—to go and be in Mission
Control and support the mission. There’s no requirement to do
that. It’s more of a perk, “Hey you’ve got us this
far, would you like to come see how things work here.” Because
I spent six months in Houston I’ve never gone like Angie has
done this time, because I was fortunate enough to spend time in Mission
Control when I was there.
For me like I said, that’s usually when I try to catch up on
some stuff at home before the mad pace starts again. We’re of
course paying attention to what’s happening on orbit. The main
thing is—if we weren’t at the end of the program—the
main thing I would be concerned about is if there is anything that’s
not working. Hopefully that’s not going to impact their mission.
Hopefully they can still accomplish their mission goals. If it’s
not working what are we going to have to do here to get it working
again? So we’re already thinking about that if they have an
issue.
Like recently I think it was [STS]-131 we had the Ku-band failure.
We were saying to ourselves, “What? It worked fine here; what’s
going on?” When something like that happens we start thinking
what kind of retest are we going to have to do. Are we going to have
to change out an avionics box or the whole Ku-band antenna? Do we
have a spare? So we’ve already started that work prior to landing.
We’re interested in hearing how things are going so we can determine
what it is going to mean for turnaround for the next launch. Luckily
133 was a phenomenal mission.
I was so happy that the crew had no issues to work in regards to the
Orbiter. Being on the runway after landing, that’s one of the
perks of being a flow director. We get to greet the crew when they
get off the vehicle. For 133, each one of them, when they got off,
said Discovery worked phenomenally. They had no concerns, no issues.
Of course I’m lucky enough to hear it directly from them, and
I get to go back to my team and pass the message along.
That’s what we were hoping for. Of any of the missions, we wanted
the last one to be where the crew didn’t have to worry about
Discovery at all. They’ve got work to do. Plus it’s their
last one with Discovery. It’s their last one as an astronaut
on an Orbiter. They get some free time up there. We wanted their free
time to be free time, not, “Oh we have to go work on a Ku-band
antenna” or something like that.
So I was just so happy that every single one of them made a point
of saying gosh it was just perfect. What a way to go out, that’s
exactly what we wanted, was to end on such a positive note. We’re
not done yet because we’ve got to get to Smithsonian. That’s
a big job, but I’m confident that we will stay focused and do
just as good of a job on that as we have in processing Discovery over
all these years. I’m really impressed with the team, especially
because it’s a hard time for the contractors. We’ve got
a lot of people that are leaving that don’t want to leave, and
they don’t have a choice. That’s tough. A lot of my very
good friends have already left or are leaving next week.
So to remain focused through that, the folks that are still here.
Even the ones that are staying don’t feel real good about it.
If their buddy is leaving and they’re getting to stay, they
don’t feel great about that. I’ve never been through a
mass layoff like this before. It has definitely been a hard time.
But I think that United Space Alliance has done a great job of trying
to help the workforce find new jobs and not be left out in the cold.
USA didn’t have to do a lot of the things they did, but they
did those things because that’s how much they care about the
workforce. Even talking to USA employees that are leaving, they’ll
say the same thing. “Gosh, we’ve been given every opportunity
to find new jobs. All the assistance we could even ask for. Do we
want to leave? No. But if we have to at least they’ve made it
as painless as they could.” I think that says a lot, not just
about USA, but also about NASA because I’m sure we have influenced
that as well. This wasn’t USA’s decision for the program
to end. I think that we as an entire agency team have handled it very
well.
Ross-Nazzal:
You’re going from a team of how many down to how many?
Stilson:
Normally our full processing team is about 1,000 people at Kennedy
for a whole processing flow. I don’t yet know how many people
I’m going to have on my transition and retirement team, because
of the contract negotiations, but it will be much less. I’m
guessing probably 60 or so. So it’s going to be a real small
team. There’s good and bad about that. It’ll make us closer.
When you have a smaller team it’s easier to be closer, but that
means a lot of work for people that normally we would have spread
out over multiple people.
Ross-Nazzal:
Tough time, but I’m glad to hear you’re positive about
it. Exciting though too to have the Orbiters in different parts of
the country where people can see them up close.
Stilson:
Exactly. That’s going to be great. It’s going to be neat
to go back after it’s all done and they’re in their final
display configuration and see them there, because that’s going
to be several years down the road before they have them displayed
how they want them in their permanent facilities. I think everybody
will enjoy doing that. From what I can tell, all the display sites,
all four of them, are really conscientious of representing the team.
Not just, “Here’s this incredible vehicle here that flew
in space. But here’s the team behind it, and what they did to
make all this happen.”
So I’ve been very happy to hear them already talking about that.
Asking for ideas of how they better convey that to the public. It’s
not just about the hardware, there’s a heart and soul behind
it. That’s the workforce that has cared for these vehicles for
all these years.
Ross-Nazzal:
Are you working moving Enterprise up to New York?
Stilson:
Yes. When we drop off Discovery we will pick up Enterprise and immediately
go up to JFK [John F. Kennedy International Airport, New York, New
York]. Actually it’ll take us about a month before we can get
all the equipment and people there to offload. So the Intrepid Sea,
Air & Space Museum [New York, New York] will have to keep Enterprise
in a hangar on top of the 747 for about a month. We’re refining
schedules right now, but it will be about a month before we can actually
offload. Then once we offload they’re going to store Enterprise
at JFK until they have their permanent facility ready. So they’ll
have it at JFK for a couple years, but they’re setting it up
so that they can bring the public in to view it there.
That was a stipulation that NASA gave them. You need to, within a
year, be able to display these vehicles. You can’t take three
years before the public can see them. All of the display sites are
having to abide by that. California is the same way. They’re
going to have a temporary display site. As well as the Visitors Complex
here at Kennedy. So all of the sites except for the Smithsonian are
going through the process of having a temporary site while they’re
working on their main site.
Ross-Nazzal:
I look forward to seeing them. Thanks very much for your time today.
Appreciate it.
Stilson:
Absolutely.
[End
of interview]