NASA STS Recordation
Oral History Project
Edited Oral History Transcript
Terrence
R. White
Interviewed by Rebecca Wright
Kennedy Space Center, Florida – 12 July 2011
Wright:
Today is July 12, 2011. This interview is being conducted with Terry
White at the Kennedy Space Center [KSC] in Florida in the Orbital
Processing Facility One [OPF-1], as part the NASA STS Recordation
Oral History Project. Interviewer is Rebecca Wright, with Jennifer
Ross-Nazzal.
Thank you so much for taking your time with us this morning, Terry.
Start by telling us how you became involved with the Orbiter.
White:
Okay. I started out as an Orbiter test mechanic. Basically that’s
a mechanic that will work on the Orbiter. I started before the first
Orbiter arrived at Kennedy Space Center, so I started building the
servicing panels in a machine shop in the VAB [Vehicle Assembly Building]
that would later service the vehicle itself.
Wright:
This was in 1979?
White:
Yes. Because of the extensive tile work that Rockwell [International
Corporation] knew had to be completed on the Orbiter, they took a
lot of mechanical and electrical techs [technicians] from KSC, trained
them here to do tile work and then loaned us to the Palmdale [California]
facility to augment them in working on the vehicle. This was mostly
to train us so when the vehicle came here we could finish the tile
work. In those days, NASA envisioned the tile to be a onetime job,
you install it on the vehicle, and then you never mess with it again
for the rest of the Shuttle history.
Wright:
That didn’t work out, did it?
White:
No, it did not.
Wright:
Tell us about those days at Palmdale and then how you transition that
knowledge here.
White:
We were loaned out there. Palmdale was a union shop, and we were not
a union shop here, so there was quite a bit of friction. Eventually
they allowed us to go to work, so we actually went out, worked on
the vehicle, learned how to install the tile on the vehicle, and then
we were sent back here to go back to our regular job. When [Space
Shuttle] Columbia came here on Easter weekend, most of us were loaned
to the OPF to start work on it.
My first function was to actually start receiving the thousands of
tile that were going to be shipped here to later be installed on the
vehicle. In those days, you had to be a certified tile technician
just to handle the tiles, so the logistics folks here weren’t
allowed to touch the hardware. Along with a half a dozen other techs
and myself, we did the initial receiving of thousands of tiles coming
into KSC. Eventually, we trained the logistics folks and certified
them to handle the hardware.
Wright:
How did those get here?
White:
Those initial tiles were shipped mostly in large shipping containers
containing 40 or more tiles, individually packaged in small, basically,
twelve-by-twelve boxes. We had to unwrap them, do visual inspections,
document any issues that were with those tiles, and then work with
the engineers to repair or replace the tiles. In those days it didn’t
take much of a crack or a chip in a tile and it was scrapped, so we
went through a lot of tiles in the earlier days.
A couple of months later I was sent up to the Orbiter Processing Facility
here in OPF-1. At that time OPF-1 was the only bay that was capable
of accepting an Orbiter. OPF-2 was still under construction on the
inside, and OPF-3 hadn’t even been dreamed of. I was sent up
here, promoted to a supervisor, assigned a second shift and given
a crew of technicians to actually install the tiles on the Orbiter.
My first assignment was what was considered part of the midbody. I
had the wings, upper and lower. I had the mid sidewalls and I had
the payload bay doors.
Wright:
Tell us about when Columbia got here and the shape that it was in
and then that whole process from there.
White:
Columbia arrived on Easter weekend. There’s a picture downstairs
I’ll show you later of what it looked like when it rolled in.
But there was a lot of tile work that had not been done. There was
a lot of other work (mechanical, electrical and especially the vehicle
testing) that hadn’t been done. They wanted to get it down here
and start running the Orbiter system testing here at KSC while we
completed the tile work. When it arrived there, there were many green
areas that had not yet had a tile installed. There were some areas
that they had never put the first tile on, and there were other areas
that they had put on and realized there were problems with that, so
we actually lost some tiles during the ferry flight on the way out
here.
I don’t know exactly when they realized it, but part of the
reason the tile came off is we had not hardened the bottom of the
tile. The materials and process engineers realized that we had a problem
with the bonding of the tile. On the back of each tile is a Nomex
pad, called a strain isolator pad. That’s actually what is glued
to the ship and glued to the bottom of the tiles, so tiles are not
directly glued to the aluminum. Well, this strain isolator pad would
peel right back off. If you pulled it directly perpendicular to the
vehicle, it was strong, but if you caught a corner of it, it would
peel right off.
The fix for that was to take the tiles back off the ship, go through
a process called densification, where actually we hardened the bottom
of the tile. We glue a new pad to the bottom of the tile. Now you
cannot get that new pad off without skiving it off with a razor tool.
As a result, everything that Palmdale had put on the lower surface
of the vehicle already had to be removed, densified, and reinstalled.
In Palmdale they installed tile, the majority of them, in a method
called array bonding, where there is a fixture that it’s about
four feet by four feet, and it holds in the neighborhood of forty
to fifty tile, and they put all of those tile up at once, so you’re
actually bonding a lot of tile at one time. Here the array tools did
not work like they did in Palmdale, because basically they started
out with a completely empty structure. So we had to turn around and
do what we call individual or single tile bonding. Though we may bond
four, five, or even nine tile at one time, we didn’t bond them
in the array fixtures.
Wright:
How many tiles were you talking about?
White:
Columbia had over 31,000 tiles on it. Now, in the two years that we
redid all of this work and completed those areas that had never had
tile installed on them, we did not get the entire vehicle densified.
We did get the lower surface tiles, the most critical tiles on the
ship, we did get them hardened. As a result, when we flew STS-1, we
lost a portion of tiles from the upper surface. It wasn’t always
a whole tile. Columbia had what was called dice tile because of the
flexibility. Rather than have an entire eight-by-eight tile on the
upper surface, we actually cut that eight-by-eight into sixteen pieces,
and they were still held together by that strain isolator pad, but
that allowed a lot more flexibility. We lost some of the pieces of
those tiles, so we did not necessarily lose a whole tile. There were
some areas where we did lose whole tile.
Wright:
When did you learn during that mission that those tiles had been lost?
White:
We didn’t have the capability we have today to view the entire
Orbiter while in space. We knew we lost some because there were some
at the launch pad. So we knew we had lost some tiles. There were many
other issues at the launch pad after STS-1. When the vehicle returned
and landed at Dryden [Air Force Base, Edwards, California] is when
we got the really good look at it and noticed how many tiles were
gone.
By then I had been transferred to the forward section, so I became
the forward supervisor still when we were processing for STS-1. As
a result, we had to remove a little over 400 tile just off of the
forward section after STS-1 in preps [preparations] for STS-2. Now,
some of those were where we had lost a tile or a portion of the tile.
Some of them we removed because the tiles were chipped; others because
they broke. There were some tiles that flexed more than they expected,
so we had broken tiles.
We had to take tiles off for access. Antennas are installed right
over the tile, so if we had a problem with an antenna, then we’d
have to remove the tile to get to that. In a lot of areas where the
original designers planned for us to open up things, like just to
get the side hatch open, we have panels and the tiles bonded to an
aluminum panel, we can take the panel off without debonding the tile.
People don’t realize it; there’s six hundred doors and
panels on this vehicle that come on and off as part of its processing.
Wright:
Wow.
White:
Yes. You sound like the president now. “Wow.” [laughter]
I gave President Obama his tour.
Wright:
I saw that picture.
White:
Most of his comments were, “Wow. Really? I don’t believe
that.”
Wright:
It’s more and more that we have learned during the years that
we’ve been doing this that it doesn’t matter where we
go or who we talk to, there’s always one more “wow”
that we find, because there are so many intricate pieces that work
on that Shuttle.
White:
There are twenty-two major systems on the vehicle, and they only call
me a subject-matter expert of one, and because of all the million
components that make up the thermal protection system, that I usually
refer to as TPS, I don’t know everything about it. It’s
too large and complicated. I have the honor of giving many distinguished
guests their tour around the vehicle when they visit KSC. Even the
people that are escorting them, who have been to the OPF multiple
times will comment they learn something new each time they follow
me. Their common comment is “I didn’t know that. I didn’t
know that.”
I tell them, “I don’t teach you everything I know in just
one visit.”
At any rate, back to the forward. As well as tiles for access, then
we take tiles off for inspection. We take them off to look for potential
corrosion underneath. We take them off to look and see if there’s
any hydraulic fluid leaking. And we take them off to evaluate the
sub insulation, that strain isolator pad that’s underneath the
tile.
Columbia had a lot of external heat sink, and it’s installed
underneath the tile to provide extra protection for the aluminum in
case any heat does get through the tile. The original designers were
very close to coming up with exactly what we needed. Most of the mods
[modifications] we’ve done over the years have been to lessen
the insulation, take away some, make it lighter, make it thinner,
but we have done a few areas where we actually had to go in there
and make them thicker or change from basically the white tiles, which
are low-temperature tiles, and replace them with the black tiles,
which are high-temperature tiles.
A fine example of that is if you look at the first few flights of
the vehicle and you look at the Orbiter maneuvering system, those
big OMS pods are at the back of the payload bay, you’ll notice
the leading edge of them is all white. Later on, we did what we referred
to as the eyeball mod, but there were two areas on the OMS pods where
we replaced the white tile with black tile, so there’s two areas—they’re
not quite circular, but from a distance they look rounded, and that’s
just where there was more heat coming up to that area than we expected
and it took several flights to realize that and then go modify them.
Wright:
How did you determine that?
White:
That was quite a few levels above me. At that point, I’m just
a supervisor, supervising the crew. But they had done some analysis
on the temperatures, and the tiles are designed to protect the Orbiter
so that it doesn’t exceed 350 degrees [Fahrenheit] underneath
the tile. That’s the aluminum structure. The OMS pods are a
composite structure. They have the fuel and the oxidizer tanks right
inside. We have to keep that structure less than 250 degrees. So in
their analysis—and Columbia had a lot of instrumentation; it
had thermal couples, which are thermal sensors, all over the place—they
had realized we were getting higher than that, just in that concentrated
area where the way it was coming up over the wings and down the sidewalls,
it was coming right up against that Orbiter maneuvering system.
I had a couple of people tell me in their earlier history that they
were doing data analysis and came up with that issue, but it took
a while to convince the program that it really was a problem. Once
they were convinced, we did the same modification on all of the Orbiter
maneuvering pods.
Wright:
You mentioned that the techs were installing these, of course, one
by one, and I’ll get back to the chronology here for a minute,
but I was curious about the analysis that you knew you had to make
those mods, but have there been times that the technicians have discovered
things or analyzed things that actually worked their way up into the
channels instead of coming downward?
White:
Yes. Yes. A fine example of a tech coming up with the fix is STS-114,
when we returned to flight after the Columbia incident [STS-107 accident].
It was the first time we had the ability to go look underneath the
vehicle. We knew in the past that we had lost gap fillers. We didn’t
know exactly when we had lost them, but in flight. We knew when it
came back there should have been a gap filler there, and it didn’t
return with one.
On STS-114, the first time they looked underneath, they saw two gap
fillers protruding. They were sticking out. So they sent an astronaut
by the name of Steve [Stephen K.] Robinson out to do an unplanned
space walk, and he went underneath, and we knew by looking at the
pictures, all he would have to do is grasp them with his fingers and
pull them out, which he did.
As a result, they wanted us to come up with a process that would ensure
that would not happen again. So we did a lot of testing, and one of
our technicians, a man by the name of John [E.] Kuhn, came up with
a solution. We had a lot of help from all around the country, but
John was working on the project and he came up with the best solution
for how to install those gap fillers without them coming out again.
In the early days when we installed them, and it’s a very thin
glue line, we pull-tested them to four ounces. In other words, we
put a piece of string through them, put a gauge on them, and pulled
them. As long as they passed four ounces, we thought that was acceptable
in one location. We realized after a while, four ounces wasn’t
quite enough, so we increased the pull test to eight ounces. That
seemed to work. After [STS-]114, when we came up with a new method;
we increased our pull test to multiple locations—in other words,
center, both ends—and increased it to five pounds. In our testing,
we could pull them to 70 pounds without failure. The only thing is
the structure won’t take a concentrated pull of 70 pounds. The
Center Director gave John a nice award for that, but that’s
a case where the technician gets a lot of help from a lot of engineering,
but bottom line is he does it every day and his method of doing it
came up with the most acceptable.
Wright:
Let me walk you back, since I jumped ahead, back to STS-2 and the
differences of [STS-]1 and 2 and your methods and the processes and
how they changed.
White:
[STS-]1 was initial installation, like I said, a lot of green areas.
[STS-]2 was going out there and looking. Now, during STS-1, we had
come up with a method to repair some tiles. Initially, the slightest
little crack, we were taking them off. A little chip, the tile was
taken off. And it was a very fragile—the coating’s about
the thickness of an eggshell and easier to damage than an egg. So
having to work around it, we damaged a lot of tile, which meant we
took them off. But we came up with some repair procedures so we could
go out and fix some short of replacing them. We had to do an initial
100 percent inspection on the entire vehicle, nose to tail, shining
lights down in every one of those gaps and looking for any charred
potentially. We learned some of the areas we didn’t quite have
the gaps right.
The thing that probably showed up the worst was if a tile was not
flush to the tile next to it. We call it a step, where you have the
second tile in the row slightly higher, and that heat traveling across
the bottom of the vehicle contacts that leading edge of that tile
that’s sticking up a little bit, and it diverts that heat down
in that gap. So we were scorching down in the gaps. We learned a lot
about that from STS-1 and STS-2.
STS-2 was a unique flow, because we had all of those undensified tiles
to replace. We had all of the damaged tile, etc. One of the things
we had to do was replace a lot of the barriers. Around all of the
doors on the vehicle, you have a seal. There’s different designs
of the seals, but they’re what keeps the heat out around all
the movable surfaces. Most of them are heat-resistant quartz or Nextel
fabric. They have an Inconel spring on the inside but they actually
compress when the door closes. Well, a lot of them were severely damaged
on STS-1, frayed, so we had to replace those. You have to get all
of the tile work done on the nose before you start the first work
on the barrier, so it becomes a serial job instead of a parallel job.
We spent a lot of nights, weekends in here replacing all of those
barriers.
In those days, you could not complete the barrier work till you got
to the Vertical Assembly Building, basically because that’s
where we closed our landing gear for flight. We rolled out of here
on our tires, got over there, lifted the Orbiter up with the big sling
that we’re going to use to lift it, and then we brought up hydraulics
and closed the landing gear. Once we took it into its vertical position
and mated it, then we had to go up there and finish measuring, and
there were 3,200 plus locations, and you had to measure the flushness
and the gap by hand. This was performed several times while in the
OPF. The final measurements were taken after you got stacked in the
Vertical Assembly Building.
We worked twelve-hour days basically seven days a week in here getting
the Orbiter ready for STS-2. Once we got to the VAB, we completed
all of the barrier work. Shortly before rollout of the OPF, we left
a platform extended, we raised the elevon into the platform and severely
damaged the elevon. So first thing you had to do was remove all the
damaged tile. We actually had to remove the damaged structure and
replace some of the structure. We completed the structure work before
we left the OPF, but we did not get all of the tiles replaced. Even
though I was a forward supervisor, I was assigned that job once we
got to the Vertical Assembly Building. I took my techs I was used
to working with, went down there and started installing tile on the
elevons. We did not finish until we were out at the pad, so we were
out at the pad climbing up on the mobile launch platform, seven layers
of scaffolding, to get up to the elevon, out in the weather, and installing
the tiles on the elevon.
After we finished that repair work, we went back to eight-hour days
for a couple of days, and then we had an oxidizer spill at the pad.
The oxidizer ran down the right-hand side of the forward. As a result,
we had to remove and replace 386 tiles at the pad. The job’s
a little trickier out there because the Orbiter moves in the wind.
It moves back and forth out there, which is really hard to maintain
your bonding pressure on a movable Orbiter. But the oxidizer didn’t
hurt the tiles. It really didn’t hurt the adhesive. It turned
the paint underneath to a liquid, so the tiles were starting to slide
off.
The first night after that happened, myself and two technicians stood
up on a platform 207 feet in the air and literally held the tiles
in place with our hands to stop them from siding, and would take them
off one at a time and hand them to someone else. They were contaminated.
They had oxidizer all over them. We put them in bags and then we sent
them to the KSC ovens and to the ovens at Patrick Air Force Base [Florida]
and basically baked the oxidizer out of them. It did not hurt the
tile when we increased the temperature, but that’s the way we
got the oxidizer out so we could reuse the same tile.
The experts said, “Well, it’ll take you several months
to get this done,” and in three weeks we were done and we walked
away from it informing the powers to be that they could continue with
launch preparation.
Wright:
The three-week period, was that part of the process that you and your
team helped develop so that you could expedite this and keep it on
schedule?
White:
Yes, we came up with the bond plans. Interestingly enough, when something
like that happens, you get a lot of extra help, which really helped
us expedite the process. But we had to come up with different ideas.
Actually, because it was a large area that had to be repainted, we
brought the guys from corrosion control to help paint it, because
we usually paint small sections. By utilizing them, they came up with
the equipment to paint large areas, so they did that for us. We just
had to come up with some new tooling ideas. We didn’t bond out
at the pad normally, so there was a lot of changes in that.
Then, like I said, we had people expediting. We had a line of people
standing there. If a tech needed something, he didn’t have to
go all the way back downstairs to the tool crib to get it. We had
runners that did things for us, so they stayed right there. We actually
created a shop in one of the crane rooms high at the pad. We got it
air conditioned and turned it into an office and a processing area
and took tables up there and whatever was necessary. All we had to
do was say, “I need,” and somebody got what we needed.
But still it was the same handful of technicians that had to do the
work on the Orbiter. We had around-the-clock engineering support.
Around-the-clock whatever we needed, they were there.
Wright:
STS-2 is quite a unique story in itself.
White:
Yes, it is. [laughs] Just for what we had to do simply because of
[the leak], and amazingly enough, we put all of the same tile back
on.
Wright:
Tell me about when it returned. Were you happy with what you saw on
the Orbiter?
White:
Oh, yes. When it came back, STS-2, we learned some new issues. Basically
there was a few tile we hadn’t hardened, but most of the tile
on the vehicle, not only the forward but the other areas, we had taken
off the ship, we had hardened them and then put them back on or put
a new one on in their place. Sometimes they’re just too fragile
to take them out. There’s no sense putting them back on, because—well,
I’ll get to that when we get to how you actually bond the tile.
Wright:
At what point as you were coming through those first test flights
did you feel that your tiles were going to be secure?
White:
We were still learning things damage-wise, but I had a lot of confidence
in the tiles, especially after STS-2 when we hardened them and put
them on. Historically, we do not lose tile. They can be severely damaged
and they still do their job. But now when we lose a tile, it will
fail what we call through the M-plane of the tile. The bond line is
still there, but halfway through the middle of the tile, it breaks.
Tile, similar to wood has grain. We learned that on some we didn’t
have the grain in the right orientation. So whenever we find that
on one area of the ship, like it’ll be [OV] 104 [Space Shuttle
Atlantis], we had one on the back that on ascent shortly after those
main engines ignited we saw in the video this tile coming down. Well,
we didn’t lose the whole tile. It was about two inches thick,
and it broke through the middle of the tile. When we went back and
analyzed it, it wasn’t the right grain. There’s different
strengths of the strain isolator pad. It was a weak tile on a strong
pad. So the tile gave, but the bond line was still intact.
Once that happened, then we went and replaced not only to all of those
tile that had that case on 104, but went to [OV] 103 [Space Shuttle
Discovery] and [OV] 105 [Space Shuttle Endeavour], and replaced those
same tiles. We went anywhere we had a weak tile and we replaced them
with a stronger tile. We were constantly learning that through the
program. When we found something out, we’d go check the other
vehicles, and we do it not only with the tile; we do it with anything
else. If we have an electrical issue with one, then we go look at
all of the others in the same scenarios.
Wright:
Are there differences in how the tiles fit on the different Orbiters?
White:
Yes, there are. Not so much the different Orbiters, but where they
are on the Orbiter. Based on the angle of reentry, there are some
areas that get a lot hotter than others, so they have a lot smaller
gaps. Then you have the tiles that are on the movable surfaces like
the elevons, the body flap, the vertical or rudder. Where they move
a lot, those surfaces move, those tiles tend to move a lot more so
we have a bigger gap in between those.
If you go to the nose of the vehicle, the gaps up there between the
tiles have to be 19/1000th of an inch and can’t exceed 30/1000th
of an inch. So you don’t have much tolerance. You go to the
back of the elevons, they have a 200/1000th wide gap between them.
You go up to the base heat shield, and you could have 100/1000th play
where up front you only have 11/1000th. So it’s strictly based
on how much movement they actually are going to have and where they’re
located on the vehicle as to how much heat they’re going to
see. We have some tiles that do see 2,300 degrees. We have some tiles
that see less than 200 degrees.
Wright:
Let’s talk about the tiles. You said you first got that shipment
from Palmdale.
White:
Yes.
Wright:
At what point did they quit shipping in and you began to do the tiles
here?
White:
I don’t remember exactly. It was sometime later in the eighties
when we actually built a facility here and got qualified to actually
manufacture the tile here. In the earlier days, Lockheed [Martin]
is the one that came up with the tile, so NASA bought the majority
of the tile from Lockheed. Rockwell got certified to actually build
tiles in Downey [California] and Palmdale, so they would build what
we referred to as the close-out tiles. Earlier I mentioned the array,
where you’ll bond fifty tile and next to them another fifty
tile. Well, there’s a gap in between for your tools. Then Rockwell
built the tiles that went in between the arrays, so Lockheed built
the ones that were design or they had the computer information for.
So we were receiving tiles from Lockheed. We were receiving tiles
from Rockwell. But in the earlier days, if we’d get a tile that
didn’t fit, we had pattern makers. We still have them today.
But we have pattern makers that actually go out there and make a foam
pattern of exactly what the engineer wants that tile to be. In those
days, we would package that foam pattern, ship it to California. They
would manufacture a new tile, ship it back here, and we would fit
it and then we would continue processing them here. We had learned
to harden them here, and actually would harden them, go through the
rest of the process of getting them ready.
In the earlier days when we would get into what we’d call a
schedule crunch, we even had astronauts that would fly to California,
pick up particular tile and fly them right in here to the landing
strip to get them for us. We learned in the earlier days, after STS-1,
which tiles were susceptible to being broken, and we would actually
keep spares so that once we got one to fit, we would build a spare
and have it ready, like the corners of our landing gear doors. I talked
about those seals that went around them, the thermal barriers. They
put a high load on the edges of those tiles, so when we would close
the doors, lots of times we’d snap a corner off. It takes ten
days to two weeks to replace one anyway, and if we have to wait for
days for one to be shipped from California, we would really impact
the schedule, so we built spares. We had maintained spare sets for
over the antennas, because we’d get all the tiles bonded over
an antenna, then the antenna would fail and we’d have to take
it back out again. So we would have spare antenna tiles to install.
Wright:
Talk about the technicians and how they’re trained and your
turnover. What they do is so intricate.
White:
Initially, like I said, a lot of mechanics and electricians were trained
in tile, taken from the pad, from the Vertical Assembly Building,
from the mobile launch platform, all that, and put to work in tile.
Also, prior to STS-1, we brought a lot of the California people that
had been working the original build down here, and then we hired a
lot of people for three to six months in the summer of 1979. Some
of those people are still here.
They were hired to complete the tile work. It’s not something
you learn anywhere else in the world, so we didn’t go out and
look for a specific area of expertise. We just found out that people
working good with their hands adapted real well. In the earlier days,
they hired a lot of people that didn’t have a lot of experience
working with their hands and then we trained them. We found some of
them did not become a good tile technician, but that person became
a very good paperwork person, so you had some people that were very
good at tracking the paperwork, so we put them into different functions,
and you find the fit of each person.
Wright:
How many technicians does it take for each Orbiter or how many do
you like to have?
White:
Well, it’s varied. There were hundreds and hundreds in the early
days. Now we don’t have nineteen TPS technicians in an entire
bay. Then I had nineteen TPS technicians just on one crew on second
shift in the forward, and we had crews all over the vehicle all three
shifts. Then there was a lot of initial installation going on. Once
we actually got the vehicles down and a lot more repair criteria,
just in the forward for STS-2 we did over four hundred removals. Prior
to the Columbia incident, we were less than 70 removals for the entire
vehicle. Out of over 24,000 tile on the vehicle, we removed less than
70, and, again, some of those are for access. The last few flights,
we’ve averaged about 125 removals. Of course, after the Columbia
incident, our criteria changed. Some of the things that we could do
prior to that in the way of repairing a tile after all of our analysis
from high-speed impact says we’re not going to do as many repairs
on the tile or as large a repair.
Wright:
Could you give us a few more details about those criteria that changed
after Columbia?
White:
One of the things that changed is we do a thing called a plug repair
on a tile. I don’t know if you’re familiar, but if you’ve
ever seen anybody fix something in wood where they bore out a hole
and they glue a wooden dowel in there, it’s basically the same
concept. We don’t remove the tile, but we drill a hole into
it on the ship, and we have another piece of tile material that is
a cylinder and we glue it in with ceramic cement. We go and attempt
to pull it back out. So basically for large damage, we just put a
new plug of tile material in the damaged area.
We have a repair method for small damages that’s commonly done
called a putty repair. We use dental drills and do what is called
an undercut. Basically we bevel out the edges so it will help lock
this in. Next we mix a putty material that’s made out of the
same material that the tile’s made out of, and additional materials
as well, but we pack that in the void like a paste. We heat-cure it
and then sand it down to restore the exact same contour, waterproof
that. It takes about three and a half hours to repair a tile versus
the ten days to replace one. The only thing is the majority of tile
material is nine pounds per cubic foot. Some of them are as much as
twenty-one pounds per cubic feet, but the repair material is sixty-eight
pounds per cubic foot. So you’re adding a lot of weight. We
go in there and fix small spots in the tile, but not large areas,
simply because of the weight you’re adding.
After the Columbia incident, they want us to take out any of the larger
repairs, replace the tile, because we were concerned about one of
those repairs coming out and becoming a high-speed bullet. We actually
built hundreds of repairs that they sent out and shot them through
the canons just to see what would happen, through the high-speed impact
guns, I guess is the proper name.
Wright:
And what did you learn from those?
White:
We learned that a large repair liberating could cause a severe damage
to anything aft of it. If we lost a repair on the forward, it could
potentially take out one of the wing leading-edge RCCs [Reinforced
Carbon Carbon]. It could cause severe damage around the main landing
gear. It’s like a chunk of rock coming out at a very high speed.
Wright:
Were you able to see those tests in person?
White:
No, I was not. I supplied a lot of technicians to go do that testing.
No, I stayed here working on additional projects and just saw the
results. In today’s age, they can send you the videos so you
don’t have to be there in person. But I have had a lot of discussions
with the guys that were doing the high-impact stuff. They came here
to KSC to brief the rest of the workforce about why you’re having
to take those and no longer something you’ve been flying for
twenty years and now take it out, and here’s why.
Wright:
The other Orbiter that we lost was Challenger. What impact did that
have, if any, on how you were processing your vehicles?
White:
Other than the impact that it was probably the best vehicle to process,
Challenger was a workhorse. They all have issues from one flow to
the next, but it seemed like we got it processed; it went back out
the door; it did its job; came back; landed again; we brought it in.
It just seemed to work over and over. Columbia being the oldest and
Challenger a little bit smoother, each vehicle we built got smoother
and smoother, but it just seemed like it was a pleasure to get it
ready.
Now, it had issues, because it was the first one we discovered that
we had a problem with our waterproofing, and, as a result, it had
the most removals of any vehicle. The tile are 94 percent air, so
the original designers have us waterproof a tile before we ever put
it on the ship, because when we get to the pad, we get rained on.
If a tile’s not waterproofed, water gets inside and it picks
up a lot of weight. Also, on ascent that water expands and actually
damages the tile, and that’s how we discovered that the waterproofing
was getting baked out from reentry. So our first method of re-waterproofing
the tiles was Scotchguard [protective seal], just like you buy for
your furniture. Every night at the end of second shift, our normal
second shift when we ended, we brought in pallet loads of cans of
Scotchguard, and we would stand under the Orbiter and literally spray
one-inch strips across every single tile and the gaps all the way
around, and we did that. Those vehicles had over 30,000 tile on them,
so that was a lot of work to re-waterproof it.
Eventually we came up with an injectable waterproofing that was injected
into the tile, and that’s where we found the issue with Challenger.
We had been working, we were very close to rollout, getting the vehicle
ready to go. I mentioned earlier that there are some heat sinks on
the outside of the vehicle and it’s room-temperature-cured,
silicone adhesive that we put on in layers, just to give it additional
heat protection underneath the tile. Well, Challenger had a lot more
than the other vehicles.
I don’t know if you’re aware, but Challenger was not supposed
to fly. As a result, since it had been the shake, rattle, and roll
test vehicle, it looked like it’d been through a demolition
derby before it had tiles on it. To make all those surfaces, you have
to have a very smooth surface to bond the tile. You can have no deviations
greater than 19/1000ths of an inch. So we had to put a lot of that
heat sink and/or a material we called screed. It’s just a different
formula of that. But basically we put it on there and smoothed the
whole thing out. The technical term is fill and fair, because we have
to make it nice and smooth.
Challenger had many areas with the thicker RTV [Room Temperature Vulcanizing]
or adhesive on the outside. Normally the layer of adhesive is only
8/1000ths of an inch, but this had in some areas almost a quarter
of an inch underneath to smooth it out and everything. Anywhere two
surfaces came together, like where the mid body and the wings come
together, you have to make that joint smooth step-wise or flushness-wise,
so you have to fair it out for a certain length to make it smooth.
Well, turns out we had some tiles still to replace when we found out
that the heat sink underneath was soft. It should not be soft. It
should be a hardness of at least forty, and this was less than fifteen.
So anytime we find an issue, then we start taking off around it. We
have to bound it, see how far it goes. Well, we removed more and found
out they were still soft. So the Materials and Processes folks, the
M&P engineers, went out and that’s what they discovered;
the waterproofing was having this effect on the heat sink. The real
thin RTV underneath the regular tile was not affected, but the thicker
ones were. So we started chasing this. When we got done chasing all
of these issues, we had removed a little over 4,000 tile.
Now, one thing that saved us was the body flap is covered with the
heat sink. Atlantis was being built at the time in Palmdale, and they
had finished the body flap, so we took the body flap off of Challenger,
packaged it up, sent it to Palmdale. They sent us 104’s body
flap and we put it on. So a lot of people don’t know when we
lost Challenger, it was flying 104’s body flap, and 104 still
has Challenger’s body flap.
Wright:
That’s an interesting piece of history.
White:
Yes. We re-identified it. For years when you looked on the inside
tag, it still said OV-099 [Challenger], but they had us go back and
take that tag off and put one that says OV-104.
Wright:
That’s interesting. Thanks for sharing that piece.
You said that each one of them had flow issues, and you talked about
Challenger, Columbia. What about Endeavour and Discovery?
White:
I’m trying to think of which ones had what. Endeavour, being
the newest Orbiter of the fleet, didn’t have a lot of associated
TPS issues, but it’s hard to remember when you do 135 [Shuttle
missions] of them, which ones. I think Columbia was one we found a
wiring issue on the inside. Challenger was the first one we flew flexible
insulation blankets on as a test. Like I said, Challenger and Columbia
had a lot more tile than the other vehicles, because when Discovery
was being built, they’d come up with a new insulation, and it’s
called flexible insulation blanket. It’s for areas that see
less than 1,200 degrees, so upper surface, and it’s a heat-resistant
quartz cloth. It’s a quilt on the outside of the vehicle.
We flew six test blankets on Challenger in very low-heat areas to
prove that that insulation would work, and it did. We had a couple
of issues with it, but we resolved those. Then Discovery was built
with that, so that changed our TPS processing because the white tile
seemed to damage easier. They cracked easier. Now we’re putting
these blankets on. They cover a lot more area. A blanket can be thirty-by-thirty,
which is our largest ones. The largest white tile is only eight-by-eight.
So you cover a lot larger area, and they’re not as susceptible
to damage.
Wright:
Did that make the whole process more efficient?
White:
That made our processing of the Orbiter a lot more efficient. We got
better. We learned which ones we could repair and the weight of tile,
how they held up, and actually, so as a result, we got down to less
than seventy removals from one flow to the next.
Actually, one of the things that helped us—I don’t recall
which flight it was. It was one of the very early flights. But Columbia
was at the pad right before launch and got hit by a hailstorm. We
went out there that night, and there was literally thousands of damages,
and they thought a small chip in the tile, that the airflow would
erode it severely coming back.
They had us go out there, and the program decided that we would fix
what we could fix, and in this case we just hardened the resulting
material. We didn’t do a putty repair. We did what was called
a slurry repair, to the extent that we were leaning over the handrails
with brooms, with paintbrushes, with this slurry material to reach
what we could reach, because you can’t reach all the areas at
the pad. But we did what we could do that night, and they flew.
They expected them to be severely eroded when it came back, and it
was not. Then our repair criteria changed from thinking we could only
do a couple of small repairs on the tile and it was scrap. After that,
they realized it wasn’t going to, then they changed our repair
criteria, which meant we fixed a lot more tile than we took off. So
an act of God actually helped us.
Wright:
Well, that’s good to know. You mentioned earlier that you were
one of the people out there holding those tile.
White:
Yes, there were three of us that first night.
Wright:
As you had to go out to the pad on more than one occasion, did you
have specific training in safety? It was a whole different environment
from what you were used to doing.
White:
Yes. In those days, a lot of the people followed the vehicle. In other
words, if you processed it at OPF-1, you went with it to the VAB and
to the pad. When we got more than two Orbiters that changed. Some
people still follow it, but TPS-wise, the people that work on the
thermal protection system, a portion of those go with it every time.
We don’t have TPS techs at the pad. We take them from here and
then we augment, because our pad crew is small, we’ve done that
for years. But, yes, anywhere out here, to be badged for that facility,
then you have to have a walk-down of the facility. You have to be
familiar with it. So, yes, we re-familiarize ourselves every time
we go out there.
Over the last thirty-three years, our safety rules have changed a
lot. We didn’t work with fall protection the early days around
the Orbiter because of the fragile nature of the Orbiter. When I was
on that small platform that was held in place by ropes 207 foot in
the air, there was no fall protection there. We just didn’t
wear it in those days.
Actually, there was only a couple of us that were certified—like
I said earlier, you couldn’t touch tile unless you were certified—to
handle tile that had a breathing-air cert [certification]. We were
on hard-line breathing because of the oxidizer, so there was only
a couple of us. When we got up there at the beginning of second shift
and were holding the tiles on, third shift came and they didn’t
have anyone with the certs. We stayed there all night, and first shift
came the next morning and they didn’t have anyone with the certs,
so we were still there. Sometime around ten o’clock, they got
some people trained that morning and got them out there to take their
place, so there were only three of us that stood there.
Wright:
That’s like twelve hours you were there?
White:
No, that was from three o’clock in the afternoon till ten o’clock
the next morning.
Wright:
That’s an experience not many people can share.
White:
Yes.
Wright:
I can’t even visualize it. I’m not sure I want to. [laughter]
Let’s talk about the facility itself and what the facility has
to be in order to process the tile and do it effectively and securely.
White:
We did have to redesign some things in the facility. The facility
was never designed to do a lot of the work that we do. If you look
at the original plan of the Orbiter, the whole Space Shuttle thing,
it was only supposed to be in this facility a matter of hours, not
a matter of weeks. We were going to fly each vehicle ten or twelve
times a year, so it was basically bring it in, change out the payload
and go again, keep the engines in for twenty-five flights. We replaced
the engines after every flight, sometimes as many as five times.
Our normal function is to take the engines out here, they go to the
engine shop, and are refurbished while we’re doing our other
work inside the aft. When they have the engines ready and we’re
ready for them to come back, we’ll bring the engines back and
put them in. We take engines out in the VAB if necessary. We take
engines out at the pad. We actually accessed one of the engines for
an issue on Atlantis out at the pad this last time.
For safety reasons, we can’t—engine number one is the
engine up above, and two and three are down below. In here [in the
OPF] in the horizontal position, we have to put engine one in first.
We can’t lift an engine over an engine. So in the earlier days,
if we had a problem with engine one, it would greatly impact here,
because we’d have to take two and three out before we could
get engine one out. If we waited till we got in the vertical, we could
take engine one out without having to take the other two. Sometimes
the smart decision was take it there. But it’s a little bit
different atmosphere. Generally you’re working out in the weather.
Way out at the pad, you’re looking down at the flame trench
way below you.
Wright:
That’s a long way down.
White:
Yes.
Wright:
What kind of equipment changes in technology—how did that help
your processing as you went through these last thirty years?
White:
One of the biggest changes is computers. Our paperwork is still by
hand, but now the specifications, the drawings, even the paperwork
that we have to initiate is all done through the computer. Before,
you had to go up and write all that down, come down, fill out a problem
report, turn it all in. Now we have laptops. You can go up there and
enter the data right away into the laptop and electronically generate
the problem report. You still kick out a paper one to actually document
the work. We’ve tried several other things. But on a drawing
you would constantly have to go to tech [technical] data, have them
print you the latest drawing. This way you can bring it right up on
the computer, look at the view you want, print out the actual thing
you want, versus having to wait a day, two days sometimes, to get
the drawing that you need. So that helped a lot, helps us document
a lot of other things, research a lot of other things quicker through
the computers.
Initially, they used to send a lot of the problem reports all the
way back to Southern California to have them dispositioned and route
them back here. It wasn’t an overnight thing. The expertise
for the original build was located in Downey, California. That’s
where all the design engineers were. We did bring design engineers
down here, but they were only temporary, so they rotated in and out,
and about time you build a good rapport with an engineer working your
issues, then, bingo, he was back in California. You had someone else
to start over again.
Wright:
How did the processing change when Kennedy became the primary site
for landing?
White:
Actually, it enhanced it because we got the Orbiter back a lot faster.
When we get it in here, we have to offload the residual hydrogen.
There’s some other components we have to get off, so basically
that cleared us. When it landed in California, we had a lot of that
initial stuff done out there. When it went back here, more people
were man-loaded onto it right away. So until some of those tasks are
done, our man-loading in the earlier days was withheld a little bit.
It takes at least a week when it lands in California just to get it
on the 747 [Shuttle Carrier Aircraft] and get it here if there’s
no weather issues, or anything like that. Plus you’re losing
part of your workforce. You have to send all of those people out there,
support ‘round the clock out there, and including their travel
time, so you’re taking them away from processing the other vehicles
you have here. It impacted you that way. Equipment went out there
that you would need here. Now you’re waiting for that equipment
to come back. Some of it is trucked across country. Some of it is
ferried by aircraft.
In earlier days, they wanted to analyze any of the tile that were
damaged, so they were taking tiles off out there. We had to install
foam blocks, so basically you had two removals for every cavity, because
when it got back here, you had to take the foam block off, because
they were worried about the airflow just on the ferry flight. There
were just things like that that impacted you.
Then when it got here, you had the tail cone on, so you had several
days’ worth of work to get all the tail cone off, which meant
with the tail cone on, you weren’t closing all the structure
around so you could get access to all the areas. There are many areas
of the vehicle that from a thermal protection standpoint we couldn’t
go do our inspection simply because platforms weren’t in place
because of all the things, as a result of the ferry flight, that we
had to take back off.
Sometimes we’d hunt for the parts they took off out there. They’d
take them off, and it would take us a while. I think I mentioned earlier
the Orbiter has 600 doors and panels. Some of them they took off out
there. Well, you have a bunch of other work to do, and way late in
the flow you’re looking around, “Well, we haven’t
seen these six panels. Where are they?”
“Well, they were removed at Dryden.”
“Okay. Well, where are they?” And they’re still
sitting in a box somewhere. They hadn’t been unwrapped.
But that happens here too. To open the side hatch there’s two
panels that have to come off to get the mechanism to open the side
hatch. We put those in a box and we put them in what we call the white-room
truck. It’s a staircase truck that pulls up for the techs to
get access to the hatch. They were still sitting in the white-room
truck. We hadn’t brought them from the runway into here. We’re
looking and we go, “Wait a minute. We’re going to need
those here shortly at the pad. Where are they?”
Wright:
The communication issues. You’ve talked about there’s
a number of vehicles, a number of technicians. You just mentioned
again parts for here. At the height of the launch schedule, when it
was moving and moving fast, how were you able to communicate where
all the steps were, especially on the TPS, that these were being done
correctly, and if you needed one from one area to the other? Talk
about the communication issues and how did it work?
White:
Then we weren’t using a lot of computers and we definitely weren’t
using Blackberries and cell phones and all that, so we actually communicated
by, what I call, in your face. We talked face to face.
There was a lot of meetings to go over schedules, to go over needs,
a lot of communication. Like the astronauts, we had people that we
would fly to get parts for the vehicle, send them all the way to California
to do a hand-pickup to bring an urgent part back. That way it wasn’t
going through UPS [United Parcel Service] or someone else; it was
handed off directly to the guy who was going to bring it right here.
Hit me with the question again.
Wright:
The question was about schedules, especially during the days prior
to Challenger when there was a push, for turning them around and moving.
White:
And a lot of people driving the schedule didn’t really understand
the nature of what it took to make some of these things happens. In
the earlier days, they wanted, “Okay, well, you have your tiles.
Why aren’t you bonding them?” Well, if the tile is located
on the aero surface, like we have tiles to bond on the elevons and
you’re doing hydraulics, you can’t bond on the elevons
while hydraulics [are being done]. If it’s in an area that’s
a clear for a hazardous operation and some of our hazardous operations
run several days, then you’re not getting in there to do your
work. Well, a lot of the people in charge couldn’t understand.
“No, you have tiles to bond. Go bond them.”
“I can’t. The elevon’s moving.”
There’s a lot of other operations that would clear us from actually
touching the vehicle. Some of the tests required a quiet vehicle.
It was a matter of getting the people who are doing the schedule and
they’re looking at the major milestones, to remind them that
there’s a lot of small things that have to happen, and you have
to build a schedule that takes all of that into consideration. With
multiple vehicles in processing, if you only have one panel that services
the water system on the vehicle, I can’t be using it in bay
one and bay two at the same time. So there’s a lot of equipment
issues that you have to put in. A lot of our equipment is calibrated,
so if the equipment’s available, is it in proper calibration
or will we have to send it out to have it calibrated or bring calibration
folks here. So there was a lot of that, and it was a learning process
to get all of that to interface together.
We built huge shopping lists that go along with the task that says
you have to have all these things, you have to have them so many days
ahead of time to verify that they’re here, that they are in
calibration. Because you get there and have forty people show up for
a task and it stops because the tool you need is out of calibration,
then everybody’s sitting there waiting, and it impacts the next
task. There are so many serial operations here that are required to
get a vehicle ready to safely launch.
Wright:
So who is the keeper of the shopping list?
White:
The ultimate responsibility for most of it lies with the engineer.
It’s his system. It’s his task. Prior to the Challenger
incident, it laid with shop, and that’s one of the things that
that commission found, that the shop folks had too much control. But
you were the bottom line. You were the one that had to get the work
done, so you were the one that stepped up and says, “You owe
me. I need from all these different people,” and tried to enforce
it. Then they came back and said, “No, it needs to be not the
one that’s responsible, but someone different. It has to feed
to them.”
So ultimately it’s the engineer. When he creates a document,
he’s supposed to create a list of the materials he needs, the
hardware he needs, the equipment he needs. Then there are people that
look at that and say, “Okay, I need that water servicing panel
for OPF-1 for the first week of August,” and then they go to
a person who—we have people who plan the GSE [ground support
equipment] work. So they look at that and say, “Okay, that panel
will still be valid until September,” or, “No, that panel’s
no longer valid the 15th of July.” Now we have to schedule it
to go down to calibration for them to run the tests, get it all calibrated,
get it up here to support the first of August. There’s hundreds
and hundreds of pieces of ground support equipment that support it.
So it is a team effort, and all those team members have to go, “Look.
Logistics has to ship the parts up here, and, oh, by the way, we have
limited space. So you can’t ship me all the parts I’m
going to need for my flow at one time. It just won’t work.”
It has to be here when you need it, not here too soon, or then it
gets shoved to the back and now you don’t find it when you need
it, or definitely not here too late.
One of the interesting challenges over the years, especially in my
world, the TPS world is a very precise world. You can change a little
bit of something and it really affects your end product. Vendors and
suppliers change things, and now all of a sudden it doesn’t
work for us or it contaminates. Simply something like one of the things
we use for getting the vehicle clean and getting it primed—we
actually put a primer on to get the adhesive to stick—we are
limited to only two pieces of material in the world that we’re
allowed to use. These are the ones that they validated when they originally
came up with this process. Well, the vendor decided to change something
in that process, and actually it was something on his equipment, but
it added silicones to it and our tiles wouldn’t bond because
it was putting a silicone film on the aluminum, and as a result, the
adhesive was curing but it wasn’t sticking. We were having bond
failures, and we found out it was because the way they had changed
something on it. We deal with that all the time. They change adhesive.
We have certain tapes, and they had changed adhesives in the tapes,
and now when you put the tape on the vehicle, take it off, it just
pulls the coating right with it because the tape’s too sticky.
Wright:
They didn’t have to disclose that they had changed their formula
or their process to you at that time?
White:
No, because some of the stuff they supplied through the system, others
didn’t realize that what they were changing was affecting us.
The guy starts using a lubricant on the equipment that makes that
cloth; he doesn’t realize that that little bit of lubricant
over there is getting on every piece of cloth that’s coming
out. But one of them, the lubricant was only getting on the stitches
on the hemline. That was enough to affect us.
Wright:
You’re right, one small piece affects a lot.
White:
Yes. Every time you have something that doesn’t work or an incident,
you look back. Very seldom is it one big thing that went wrong or
one obvious thing. It’s something way back in all of these little
things that have to happen, and that little thing caused the issue.
Sometimes it’s very difficult to find out what it was.
Wright:
What do you do in the meantime? Do things stand down?
White:
In the meantime, we do a lot of testing. It’s very difficult
to substitute in a manned flight program. What’s valid is you
go back and research, but, yes, we constantly build test panels to
go test why did this not work, why did that not work. That was one
of our big things after the Columbia incident. There was a lot of,
“We think this is what happened, but we don’t know,”
so we built dozens and dozens of huge panels for them to fire stuff
at to test. We took doors off of Enterprise because they matched.
We built structures. Columbia and Challenger’s leading edge
of the wing was different from the other vehicles, so to exactly match
what we had on Columbia, we had to come up with some different structure.
We couldn’t just test on one of these vehicles because it was
different. We built test fixtures and we had put all the stuff on
them, and the experts didn’t think it would happen. But when
we fired that piece of foam at it, it knocked a hole right in that
reinforced carbon carbon; they did not think it would happen. But
based on everything we had seen, that’s what happened, and when
they hit it, that was the proof.
Wright:
What were your thoughts when you saw the video when Eileen [M.] Collins
turned the Orbiter over and did the back flip so the ISS [International
Space Station crew] could take the photos and you were able to actually
see the belly of your Orbiter and you could see all your tiles? What
were your thoughts of being able to see that?
White:
Just that it was amazing. We had been seeing some of it before. There
are some very elaborate cameras, not to the detail of that, but just
to watch it move around in space, because here we tend to stay busy
with what we’re doing and concentrated on what we’re doing.
People come in here and ask us about the payload, and I said, well,
I know about the different interfaces, but we never even study what
payloads they’re flying, because we’re busy enough with
doing all the things to get the Orbiter ready. People have questions
about the boosters and the tank, and I said, “I’m not
a booster guy. I’m not a tank guy. The only way I interface
with them is when we’re over there.”
The Orbiter has occupied our time and talents, so it’s hard
to look at something else. Sometimes until we get down close to the
end of the flow and we’re getting ready for the crew equipment
interface tests, we don’t even really look at the payload. Especially
since the last several years everything’s going to Station,
we put all the interfaces, all the things that’s going to support
that payload, and all that Station hardware is large pieces that went
in out at the pad. So a vertical payload goes in out there. A horizontal
payload goes in here. Now, we put all the interfaces in here and we
test it, simulate that, but we don’t actually, for the last
several years, actually look at the payloads. Now, when it comes out,
we get a chance to look at it.
Wright:
If you don’t mind, I’m going to switch and ask Jennifer
if she’s got a couple of questions for you before we run out
of too much time.
Ross-Nazzal:
Yes, actually I had a few. One of the things that we didn’t
talk about were the Orbiter maintenance down periods and the OMMs
[Orbiter Maintenance and Modification] that are done here. What impact
did that have on your schedule or how you handled the Orbiters? Can
you talk about that?
White:
Basically the OMMs, that’s why Bay 3 [OPF-3] was built. We were
very busy in the earlier days, especially when we had four Orbiters
here and only two bays, so we were constantly shuffling. We’d
have an Orbiter in here we’d be working on, one slated to land.
We would have to take this one next door and we’d have to validate
all of our equipment that we can’t validate with an Orbiter
in here, then bring that Orbiter in, de-service it, and then potentially
swap it to the VAB to get the first one back to go work. In the VAB,
we can’t do hardly anything. The stands aren’t there,
we can’t open the payload bay doors, etc., so a lot of work
we cannot do over there. We can do limited tile work, but that was
it. But basically shift them around.
NASA wanted to start doing the major maintenance on the vehicles at
KSC. After so many flights, you have to take it offline. There’s
a lot of areas that you really have to go in and look, things that
have to be changed. There were upgrades they wanted to do, and some
of them you can fit in during a processing flow, some of them you
cannot.
Bay 3 was built so we had a place to perform this extensive work.
We’d already determined not to fly from Vandenberg [Air Force
Base, California] at that time, so we took the internal structure
from Vandenberg, brought it here and assembled it in Bay 3. Bay 3
is slightly different from the other two bays because of that structure.
Some of our talent was taken over there. We hired additional people,
had to train them, and then started doing the maintenance over there,
and still we were busy enough with three vehicles in the hangars,
and NASA opted to go, “Well, we’ll go back to doing OMMs
in California.” You probably don’t want this part, but
there was probably a lot of politics involved in that. There is a
lot of work and a lot of money in OMMs, and basically you had empty
facilities out there, so there was a lot of logic behind what they
chose. But they wanted a third Orbiter processing facility, so we
took that one offline again and went and installed all the plumbing
and everything associated with de-servicing an Orbiter that it did
not have and made it an operational bay. We went to three operational
bays, still with four Orbiters. We were still shuffling things around,
but basically scheduling things right.
Then when we lost Columbia, we kind of made each one of them have
a home. Atlantis was Bay 1, Endeavour was Bay 2, and Discovery was
Bay 3. Three hangars, three Orbiters.
Ross-Nazzal:
Were there significant changes made to the TPS during those times?
White:
Yes, and when they started doing the OMMs, they wanted more weight
taken off the Orbiters, so one of the things we could do was we lightened
the TPS. We didn’t do any lighter for the tiles, but then we
had the flexible insulation blankets, and we had areas of the FRSI
[Flexible Reusable Surface Insulation] that we knew were thicker than
they really needed to be. It doesn’t seem like much when you’re
taking a thick quilt off and putting a thinner quilt on, but when
you look at the number of quilts that are on there and you can do
that in a lot of areas, we did. We’ve done mods that took us
thirty days to do a mod to shed four pounds. It’s very expensive
per pound to take that into orbit, so the more weight we can shed,
we constantly did. That was one of the big things for TPS was to go
take a lot of the upper surface. For Columbia it still had all those
tiles on there, so we removed a lot of the white or low-temperature
tiles and replaced them with the flexible insulation blankets. Again,
we saved weight and made the vehicle easier to process.
Some of the things we did, one of our extensive ones, again, back
earlier I mentioned about the seals around the doors, the thermal
barriers. Well, those have always been one of the long poles, because
they’re on the hydraulic areas, which means whenever they’re
doing hydraulics, you can’t work them, then you can’t
validate your doors until all of those seals are installed. On the
main landing-gear doors, on the external-tank doors, the vent doors,
we did mods, and instead of thermal barriers that we had to glue in
place, we came up with ones that mechanically fastened. We either
clipped them in place, bolted them in place, so if some of them were
damaged, we could take one out, clip a new one in, we were back in
business, versus having several weeks’ worth of bonding to get
it all installed. A lot of our issues are, when you’re bonding
something, if it slips slightly, you have to wait till the cure is
all done, take a look at it and go, “It slipped.” Now
you take it out and you start all over again.
That was a big issue on the nose. The redesign wasn’t mechanical.
We still had to bond it, but we bonded it using ceramic cement, and
you only had, I want to say, a twelve- or seventeen-minute work life
with this ceramic cement, but it had to cure for forty-eight hours
before you could look at it, and then when you looked at it and a
portion of it slipped, you had to take it all apart and do it again.
I finally found out. I said, “How did you come up with a forty-eight-hour
cure on this ceramic cement?”
The guys in the advanced testing said, “Well, we put it under
cure on Friday, we went home, and when we came back Monday, it was
cured.”
I said, “How about running the tests again and this time do
it on a Tuesday and come back Wednesday.” [laughter] A few months
later it changed to sixteen-hour cure from forty-eight-hour cure.
So it was a matter of the design guys don’t always look at it
from the operational standpoint. They’re looking at coming up
with something better for the vehicle but don’t realize what
it does to you.
One of the things we did was they came up with a stronger tile, and
they had already come up with one, what they call a TUFI [Toughened
Unipiece Fibrous Insulation] coating. The regular tile chips easily.
The TUFI will really take a beating. But they’d come up with
what they call a Boeing Rigid Insulation [BRI] that Boeing came up
with. It’s a much stronger tile, but it has this TUFI-type coating
that actually impregnates it. They were working on it prior to the
Columbia incident, but after the Columbia incident, they wanted to
implement it around our landing gear doors, the areas that were most
susceptible to damage that would cause a catastrophic failure.
But they weren’t sure we could fix it if one got chipped, so
if we put BRI tile on the vehicle, chipped one, do we got to sit here
ten days to replace it? The designers sent it here, and the same technicians
that repaired the other tiles purposely damaged the tiles and repaired
them, sent them back to them so they could test them, to prove that
it would work. It did, so then we started installing BRI tile on the
vehicle. We even put additional BRI for Atlantis’ last flight.
With every flow since then, we have done modification. Nothing wrong
with the tiles that were on there, but we put stronger tiles on just
to enhance the vehicle. Usually we do in the neighborhood of thirty-six
to fifty each flow of the stronger tiles.
Ross-Nazzal:
Tell us about, if you can, the inspections, the tests, the certifications
that you have to go through to verify that the TPS is ready for flight.
White:
Inspection-wise, we do a minimum of five documented inspections from
one flight to the next. Our first one is a quick look at the runway.
Of course, we can’t see all the vehicle at the runway because
we just can’t get up next to it, but we basically walk around
underneath. There’s some certain areas we measure while they’re
still hot, where the gap’s expanded, but we do a quick visual
out there, documenting that, and we’re looking for large damages.
We’re even doing this prior to having the ability to go look
underneath. We get a lot of footage on orbit now. We actually photograph
everything before we leave here. Once they get in orbit before they
get to the Station, they photograph 100 percent. We have people comparing
both. Then at the end of the mission once they leave Station, they
go out and photograph again. But we do a quick look at the runway.
Then once we roll in, we do what’s called a micro inspection,
up close, very personal, shining lights down inside the gap, 100 percent
of the vehicle. As we’re working on it in here, we continue
to inspect while we’re working, but shortly before we leave,
last couple weeks, we do another 100 percent inspection, only this
one is macro, arm’s length. We’re looking for any damages.
Then when we get to the Vertical Assembly Building, we inspect it
again. When we get to the pad, we inspect it again, and those are
all documented ones where USA [United Space Alliance] Quality [assurance]
does the inspection, involves NASA Quality in it as well, and basically
has to sign off that they have inspected all of these.
Ross-Nazzal:
Do you have to do any testing at the time anymore?
White:
Yes, we do. We still do. Anytime we install a new tile on the ship,
we attempt to pull it back off the ship. Once its cure is complete,
we put a thing that’s called a bond verification [BV] chuck.
It’s something that’s custom built for each tile. It has
a gasket and a pad, and we adhere it to the tile with a vacuum. You
can’t actually grab hold of the tile. It’s too fragile.
So we put this what we call a chuck onto the tile, we fasten the load
cell to it, and we attempt to pull it back off the vehicle. Most tile
get pulled to ten pounds per square inch, so a standard tile underneath
the vehicle, we would pull the 250 pounds to attempt to pull it back
off.
Now, that’s after its initial bond. We don’t do that unless
we suspect there is something wrong with the tile. We may set up and
go BV [test] one again. Usually if we suspect something’s wrong
with the tile, we have certified wigglers.
Ross-Nazzal:
That sounds like an interesting job. What’s that?
White:
I told you earlier the tile is on a strain isolator pad so they all
move. Well, we have people that are trained to the point that they’re
supposed to know how much is too much movement and how much is just
right. They actually go out there and put gloves on and they attempt
to move a tile just to see if it wiggles too much. If they think it
wiggles too much, we take it off. Generally if it’s in decent
shape, we’ll reuse the same tile, put a new strain isolator
pad on. Some of them historically, they’re a large tile with
a very small pad underneath them because of curved surfaces, and they
feel loose anyway because of that. So that’s just one of the
things we do.
We inspect a lot. Like I say, the six hundred doors and panels that
come off, that exposes the edge, so we can look at that. We look for
any stretching in that strain isolator pad. We look at the structure
around where we took the ones off. So there’s a variety of inspection
and evaluation, and then if something goes wrong on ascent and we
see it up there on orbit, we build test panels and we go duplicate
the damage they have in space and test it right here in the Arc Jet
Lab [Laboratory] to give them the go-ahead to come home.
It was STS-118 where Endeavour had some that you could actually see
the green structure underneath, severe damages, but their testing
said it won’t be catastrophic, so they opted to—it’s
a very risky maneuver, putting an astronaut out on an unplanned space
walk. Underneath they could potentially do more damage than they fix.
So they opted to bring it back home. We thought we’d have some
structure repair to do when it got home, and the vehicle came back
in better shape than our test article.
Ross-Nazzal:
Walk us through, if you would, how you might install or repair a tile.
You mentioned having to take things off. How do you do that without
damaging another tile?
White:
That’s most of the time now if we’re taking a tile off,
after they have several flights on them, they get brittle enough that
you’re wasting your time installing, because if I took it off
and it was still in good shape and I put it back on, then when I attempt
to do the bond verification, the pull test on it, I wind up pulling
the coating right off, just because the tile is older. So time-wise,
money-wise for us, it’s better to go put a new tile on if you
take one off.
If it’s a single tile and there’s no exposed edge like
a door or a panel or something next to it, generally we destruct it
in small pieces. We actually crunch it out, vacuum it, and that way
we don’t damage anything around it. If we like the way it fit
and we have the computer information, we actually just tell them,
“Okay, build us a like item,” and they build them right
across the street versus California.
If we don’t like the way it fits, we have several different
options. One of them is an advancement over the old method. We still
have the same pattern makers like we used in STS-1, that the guy comes
out here and by hand makes a duplicate of what we want the tile to
be out of foam. The engineer’s satisfied with the way he built
it, then we send it across the street and they duplicate it and send
us back a tile.
Or we have a thing that we’ve come up with a tool, an Optigo
tool, in the last few years that uses a laser scan, so it actually
goes up there and scans the adjacent tile and it scans the cavity,
and actually, if we’re going to use it, we’ll scan the
damaged tile before we take it out, so we know what it looked like.
We send all that information across the street to their programmer,
he adjusts that for the program there, then it’s fed to the
machinist in his machine, and he manufactures a new tile based on
that laser program. So it doesn’t save us a lot of time on a
single tile, but if we’re taking a row of tile off, like we
did to put the BRI on, it can do the scan of six, eight, ten tiles
in a row, and then you tell it where to break between those tiles
and it does that. It does save you a lot, because if you were doing
all of those by hand, you’re having one taped in, so when it’s
taped in place, there’s a little bit of movement while you’re
doing the next one, so it’s trying to keep everything fitting
together. The Optigo really, really saves us a lot on ones like that.
Then you have the historical data. If I ever break that tile again,
you go back and say, “Okay, give me that one.” If I build
one out of foam, the foam changes over time. It tends to warp, so
basically I’m back to building another one out of foam or I
trace it with the Optigo machine. Once I have it built, I can use
the Optigo machine. We have time later to save that data.
Ross-Nazzal:
You mentioned the KSC and Cape Canaveral ovens. Can you tell us a
little bit more about those?
White:
They’re actually the Air Force ovens at Patrick Air Force base
[Florida]. They have ovens for heat-cleaning certain things, and to
get the oxidizer out, we send it to them. Well, that wound up ruining
their ovens. When we were done, we had trashed their ovens. Later,
we never used it for oxidizer, but we would get hydraulic spills.
Hydraulic lines would break and then get hydraulic spills. We’d
have to take the tiles off because they had hydraulic fluid. We used
conventional barbeque grills and used that to burn the hydraulic fluid
out of the tile. The heat won’t hurt the tile. The tile will
take the 2,300 degrees. So we’d lay them right on there. We
weren’t screwing everybody’s oven up, and what we got
was what we needed. It baked the hydraulic fluid out of there. We
have heat-cleaning ovens across the street, but they’re small,
plus it’s very hard on the oven when you put all those contaminants
in. Patrick Air Force Base wasn’t very happy with us.
Ross-Nazzal:
I can imagine.
These are just a couple of quick questions that probably won’t
take any more than a second. You mentioned a dice tile. Were those
unique to Columbia? Were there dice tiles on the other Orbiters?
White:
Columbia and Challenger. This will help you. This won’t help
[someone reading the transcript] because they can’t see this,
but this is a dice tile. Basically we had the entire tile, and this
one has never been hardened, so this would peel right off. But we
glued this pad to the back of the tile and keep it under vacuum for
eight hours till it’s cured. Then once it’s done, we send
it to the machinist, and the drawing tells him exactly how wide this
gap has to be. He cuts it and he cuts all the way through the tile,
but he doesn’t cut through the pad. So basically this thing
is able to flex a lot, that the vehicle needs to do without cracking
the tile. Otherwise it tends to crack the tile. It doesn’t take
much at all to damage a tile.
Ross-Nazzal:
Where did you say those were located on Challenger?
White:
By part number, this one belonged on the payload bay door. Dice tile
were all over the vertical stabilizer, the tail of the vehicle, down
the mid sidewalls, payload bay doors, crew module. So a lot of areas
you see in white on Columbia had the dice tile on there.
Ross-Nazzal:
The other thing I wanted to ask you about, you said you worked on
the service panels when you first came. What are the service panels?
White:
These are the equipment that you use to hook up to the vehicle to
whatever it is to service, service it with water, service it with
hydrogen. These are all of the different things that you have to do
to run materials from the facility into the vehicle. They have pressure
gauges. They have flow meters. They have all kinds of different things
on there. Basically we had to build those. They give us a drawing
and tell us what kind of meters, what kind of fittings, so you drill
all these. That’s the kind of thing as we walk around, I can
say, “Okay, this is what it is,” and now it will kind
of click, but the rest of the equipment it services. Like if you go
to get work done on your car, and you go in there and look in that
shop, he’s got a piece of equipment that will spin your tires
up, he’s got a piece of equipment to do something else, all
these different things. They don’t stay with your car, but they’re
all the things that he needs to hook up and disconnect to do the different
work on your car.
Ross-Nazzal:
I think that’s it for me.
Wright:
I know you had some notes. Is there anything you’d like to check
and see to make sure? We don’t want to miss anything that you
might have thought of.
White:
One of the things you asked about, and I don’t know how much
more you want to go into, but one of the things you asked about were
some of the things that would have to do with the pad, and I already
mentioned engines. Well, there’s a lot of things, certain things,
small things inside that we changed, but one of the things was windows.
We had to replace windows at the pad before, which is way out of the
norm for what we do.
Window work is in here. We used to do a lot of window polishing. It
was hazing the windows. For the astronauts to be able to see out of
them, we spent days and days on our bellies with a really fine compound,
polishing the windows to get all the haze off. We found out it was
the SRBs [Solid Rocket Boosters] that were causing the hazing, their
thrusters as they pulled away, and the fix was we fired the Orbiter’s
thrusters at the same time, and it diverts that exhaust from coming
against the windows. We were getting out of the business of polishing,
but then after the Columbia incident, we found out that windows are
one of the weakest portions of the outside of the Orbiter. So we remove
and replace for quite a while about half the windows after each flight.
It’s a big task taking those out, getting them back in. We had
a lot of fastener issues with that.
We have a lot of fastener issues with the vehicles because they weren’t
designed to come apart. Engines were supposed to stay in twenty-five
flights, so there’s two hundred doors and panels that have to
come off the engines. Those fasteners were only designed to go in
and out a couple times. We’re taking them in and out dozens
of times, so we’re wearing out the nut plates, we’re wearing
out the fasteners. We’ve constantly done nut-plate change-outs.
Some of the areas it’s next to impossible to get to that nut
plate because of where it’s at. We found corrosions on rivets
on the inside of the mid body, so we have to take the tile off to
get to the other side of the rivet. So, we worked through a lot of
issues over the history of the program.
One of the things you asked about was inspections. We inspect for,
I think I mentioned, hydraulic fluid now. There’s nothing wrong
with the tile, but we take it off so someone else can evaluate what’s
underneath it.
Wright:
You mentioned corrosion. I guess that’s a story in itself, isn’t
it, being here [in Florida].
White:
Yes, it is. We’ve done a lot of mods on the leading edge of
the wing because of corrosion, but we’ve put it in a very harsh
environment right on the ocean, and it is aluminum, so, yes.
One of the things after the Challenger accident, in all their investigation,
TPS on the Orbiter was not a contributor to that, but we found some
other things TPS-wise that we wanted to improve. Basically they wanted
a lot more documentation. Part of the Challenger incident, we could
go replace the tile, and the documentation was three pages, front,
back, front. That was it. After the Challenger incident, it went to
twenty-one pages plus attachments of repair. It used to be you could
do sixteen repairs on one thing. Basically you put the part number
down, you checked the blocks that I did the repair, you stamped it,
and your Quality [Control, QC] stamped it. It went to like seven pages
of documentation, recording everything you used. You had to write
down the time you started this, the time you started that.
Basically they wanted a lot more, and it took us a long time to convince
them that they didn’t need that. We eventually convinced them,
“Look. We’re doing thousands of repairs. What are you
doing with all this data?” And they admitted they weren’t
doing anything, so we convinced them to let us go undocumented. It’s
the first time in the history of manned flight that we got to work
on the space vehicle with no documentation. It literally saved us
a lot. We still did the same repair, but if the Quality or the tech
saw a damage, they’d measure it. They’d say it’s
within the criteria, so they put an undocumented sticker. If it’s
a tech and he’s got the time and his supervisor says, “Yeah,
why don’t you do it,” he’d just go get the stuff
and come back, as long as he’s got the cert, and fix it. But
we did the same procedure that we would do with the documentation,
but we didn’t write anything down, and the tech would just go
and tell the QC, “I’m going to go do some undocumented
repairs on the vertical.” He would get the stuff and go up there
and he’d do them all, and he’d never record anything,
and we’re done.
I had a lot of people way up high in the NASA [Space Shuttle] Program
Office, when they’d meet me later, said, “No, we are not
buying into that.”
I said, “You did.” When you explained it to them—but
from the thing, they just could not believe they were going to let
you work on the vehicle without any documentation.
But it literally saved us a lot of time. The repair was still the
same, but we didn’t have the paperwork, we didn’t have
the tracking of this. When you saw it, you could fix it. You didn’t
have to go wait a couple of days for disposition to come out.
Then some of the other systems eventually went to more of a standard
repair like we did. They didn’t go to the undocumented. But
we created a lot of standard repairs that made it real easy. You have
this problem, here’s the fix. As long as it’s within these
dimensions, here’s the fix, period. So you didn’t have
an engineer spending a lot of time researching.
Wright:
Before we close, we all watched Friday morning as the last launch
went off, and I’d like you to share your thoughts of what you
thought of as you saw Atlantis lift off.
White:
Well, I was actually over at the press site, standing right down next
to the water, which I’m normally not. Normally I’m watching
it right out here in front of OPF 1. But I was with the BBC [British
Broadcasting Corporation] and they wanted to ask a few things. It
really hasn’t struck home as being the final yet. I told them,
for me, the final will be when it lands, because the mission is not
over, and it rolls up here to the door, and as we pull it in, knowing
that that’s it. Now it’s going in the door and it will
never come back out to fly again. Right now we still have a job to
do, and that’s the way a lot of the people on the floor feel,
“No, I’m dedicated to doing this. I’m concentrating
on doing this.”
When it is done, then I’ll go look at doing something else,
shift my mind over to something else. I think that’s for a lot
of them. It’s done it for the other two when they came in and
people knew that that was that vehicle’s last flight, there
was a lot of emotion, a lot of tears down there on the floor. Some
of the people for Atlantis get it for a second time.
When we flew [STS-]132, everybody thought that was its last flight,
and also there was a lot of emotion for that, and very few people
actually believed it would fly [STS-]135. They knew we were going
to get it ready, because it was the rescue vehicle to support Endeavour’s
flight, but they didn’t really think that it would get funded
to go fly.
Wright:
Now we understand it’s been extended by a day, so you have one
more.
White:
I hope it’s not extended by two days.
Wright:
I understand your days are limited, is that correct?
White:
Yes. Yes, because landing’s supposed to be on the 20th, and
I leave on the 22nd.
Ross-Nazzal:
Before we go, I just want to ask one more question. In 2004, [President
George W.] Bush announced that we were going to retire the Shuttle.
How did that impact the number of technicians and engineers that were
working on your system? How has that changed over the past seven years?
White:
Well, we’ve lost a lot of folks. Now, when they made that announcement,
everybody knew for years that the Shuttle was going to end. No way
were we going to get near the hundred flights per vehicle, but we
all envisioned having the next vehicle. Shuttle was approved while
we were still flying Apollo. I know it wasn’t here, but it was
approved. We had a vehicle we were working on. Bush’s comments
were, “Okay, the Shuttle is ending, but we’re going to
go with the Constellation Program.” We envisioned that the old
guys like me would take these vehicles into transition in retirement,
hopefully go help set them up at the museums. The younger people would
go over to the Constellation. We had people working in new areas,
we had people working Constellation, and then when the next administration
came along and said Constellation’s done, now there’s
nothing for the younger workforce, so they’ve been leaving ever
since that announcement.
And the last few years, we haven’t had the hectic flows that
we used to have. The flows got longer after Columbia, and so the longer
the flow, you don’t need quite as many people to get it done.
We just envisioned that there would be the next program for those
people. We knew it wouldn’t take all of them, but, like myself,
I’m a little bit short of retirement. So if I’d have had
a couple more years of transition, retiring vehicles, I would feel
I had completed the program.
Wright:
We thank you. We have learned a lot, and I know we just touched the
tip of the iceberg of what’s in your brain, so we appreciate
the time you gave to us this morning.
[End
of interview]