NASA Johnson Space Center
Oral History Project
Edited Oral History Transcript
Conrad
Wells
Interviewed by Jennifer Ross-Nazzal
Houston, Texas – 14 August 2018
Ross-Nazzal:
Today is August 14th, 2018. This interview with Conrad Wells is being
conducted in Houston, Texas, for the JSC Oral History Project. The
interviewer is Jennifer Ross-Nazzal, assisted by Sandra Johnson. Thanks
again for coming over and walking over in the heat. Appreciate it.
We ended last time reaching the pathfinder OGSE [Optical Ground Support
Equipment]-1 and 2 tests, but we did not talk about them. We said
we’d talk about them today. I thought we’d talk about
your role in those tests.
Wells: Yes.
I think I’d been talking about how these tests helped to reduce
risk for the final flight test. They were learning experiences for
the facility, for the optical staff, for the thermal staff, for the
hardware, frankly, itself to get ready for the flight test and to
reduce the risk for the flight test. That was the smartest thing that
was ever done. We learned so much in each one of those tests.
During one of them we had a water main break during the middle of
the test down in the cryopumping room. There was a 10-inch water line
main burst, and they had to turn the whole system off. Luckily that
was during a warm-up, and we were at a safe temperature. So everything
was fine. If something like that were to happen on the flight unit,
that would have certainly been more of a concern.
We learned lots of things in all these tests, especially about the
facility and thermal and optical. The pathfinder consisted of 2 primary
mirror segments out of the 18, a secondary mirror. In the second test
we had the flight Aft Optics System, which is the tertiary mirror
and fold mirror that then directs lights into the instruments. From
an optical testing standpoint, we needed all those practice runs to
get our software ready for the flight test. Processing the interferometer
data we knew would be challenging, and it was always more challenging
than we thought it would be. In each test, we learned a little bit
more and continued to progress in our processing abilities.
I think the first pathfinder test was either 45 or 60 days, the second
one was 60 days, and the third one I think was maybe 90 days. They
were long. They were grueling tests for the people that worked it.
One of the unique things about those tests—because it wasn’t
a flight unit, everybody had to take a lot more responsibility. The
team was not as big. I got to be test director for a number of third
shifts, because that’s where they always needed people to fill
in. Frankly, they were a lot of fun. It would be during warm-up or
cooldown, and things always go wrong in the middle of the night. You
always have challenges or need to make some decisions in the middle
of the night. It was a lot of fun to be there to make those decisions,
to make those calls. It was a great experience for all of us there
doing that, making these [tough] decisions.
These tests always present things that you don’t expect, and
practicing solving those problems is very important. There were times
that we weren’t warming up quick enough, or we weren’t
cooling down quick enough. You started to get a feel for how the chamber
worked. It’s a three-quarter-of-a-megawatt helium compressor.
We get a handful of trucks of liquid nitrogen a day. Dialing those
temperatures and making it work thermally was a great experience.
Keeping the hardware safe was really a thermal concern. Very often
in those early tests you were learning how to tweak things, how to
make things work, to stay within the safe range for all the hardware.
Your goal was to stay just in the—you’ve got a red zone
that you never want to get to. You’ve got a yellow zone, which
you can go into if you need to. Then you’ve got the safe zone.
You’re always trying to ride the yellow region, just outside
the yellow, because that would be a faster test, the quicker you can
go. So we were always riding through it, “Maybe can we get permission
to go a degree over, a half a degree over, into the yellow zone? It’ll
save 8 hours in the test.” You’d get approvals to do that,
because a good portion of the test, more than half the test, is the
warm-up and the cooldown. For the flight test, it took 30 days to
cool down and 30 days to warm up. You only had about 30 days in between,
30 or 40 days. So most of the test is the warm-up and the cooldown.
Our goal was to align those two primary mirror segments to each other
and phase them, to turn them from two individual mirrors, to bring
them to be perfectly flat and parallel to each other was our goal.
That first test certainly we struggled trying to get that done with
the software that we had at the time. In the months that it took to
get ready for the next test, we worked on our software.
We did a better job in OGSE-2. We still struggled; it was still challenging.
One of the problems is with only 2 mirrors it actually perhaps is
a little harder than if you had all 18. Getting the data to process
correctly so that we could converge to a phased mirror was again more
challenging than we thought. We got close probably in the second test,
but we didn’t have it nailed yet.
I think partly as a result of that, the third test, which was the
thermal pathfinder, they decided to make that an optical test as well.
There was a pretty long period of time between those two tests. They
had to bring the telescope out of the chamber and make a lot of thermal
modifications. Basically the goal of that test was to have a simulator
of the flight telescope thermally inside the chamber so that you could
practice the thermal profiles of the flight unit, you could practice
those on something that was thermally similar to the flight unit.
That took months. I wouldn’t be surprised if it was close to
a year of work to get all that done, certainly six months at a minimum.
That gave us a lot of time to process the data. There was a team at
NASA, a gentleman by the name of Kong [Q.] Ha worked really hard with
Joe [Joseph] Cosentino and Gene Olczak, the engineers from Harris
[Corporation]. The software was really developed by Gene. He was the
real brains behind the concepts, and Joe Cosentino was the guy that
got it done. He made the software user-friendly. He made the software
give you answers that an engineer could understand.
One of my goals was to be able to get as much diagnostic information
as we could out of the software to try and help us make decisions.
Joe was always ready to help us do that. We ended up with a final
product that gave us probably maybe more information than we needed,
but at times we needed portions of that information. It gave it to
us, so that when we got to the flight test it all worked. It all worked;
it all worked really well. That was really a testament to the team
as a whole but then Joe getting the details of the software, giving
us diagnostic information of individual mirror tilts and mirror pistons
for a bunch of different entrance conditions to help the engineer
be able to make the right decision. It really isn’t a process
that can completely be done by a computer. It really takes a knowledgeable
engineer to look at the data and understand what’s going on.
We ended up getting the information that we needed to get that done.
Those tests really were critical in executing a successful flight
test. OGSE-1, OGSE-2, and thermal pathfinder, those three campaigns
really helped us get ready for the flight test.
Ross-Nazzal:
You mentioned that you were a test conductor during that third shift,
when things might go wrong, if they were going to go wrong. Are there
a couple of examples that you might share that you were surprised
by?
Wells: One
of the goals of program management was always to get these tests done
as quickly as possible. How much could you get done in how short of
a period of time? I know one of the evenings that I was working, I
thought, “Well, heck, I don’t see why [we can’t
go faster].” We were told during the daytime to go a degree
an hour—or half a degree an hour—and I started looking
at the data and I said, “I don’t see any reason why we
can’t go,” I don’t know if it was 30 percent faster
or whatever it was. I said, “This is what we’re doing.
We’re going to do that. It all looks safe.” The thermal
people bought onto it. The flight hardware safety people bought onto
it, and we did it. When the leaders came in the next day, they were
very happy that we had done that. We’d made the right decision.
That was a good one.
I’m trying to think of one that wasn’t. Obviously the
broken water main was a huge event. It teaches you that as hard as
you can to try and find problems with your system, who would have
thought that the water supply, just a water supply, was the problem.
We follow these risk management procedures to look at all the different
aspects and what could go wrong. To say, “Okay, if the cryo
system went wrong what would go wrong?” We were thinking it
would be the power or the air pressure or something like that. It
turned out to be the water main.
I can’t right at the moment come up with one. I know there were
a couple. I know we called Jon [Jonathan L.] Homan in the middle of
the night one night because of something happening, and I can’t
quite remember what it was.
Ross-Nazzal:
It’s okay, memories fade. Obviously [it] didn’t impact
things too greatly. You continued on, and it led to a successful test.
Were you there when Webb finally arrived here in Houston?
Wells: When
the telescope arrived? Yes, I wasn’t there when it flew into
the airport. I was there when they loaded the shipping crate. The
shipping crate would come into a truck lock, a very dirty truck lock.
It’s interesting. You’re trying to keep everything very
clean. You’re opening these doors and 10 feet over is this very
dirty area.
You manage for these sorts of things. You’re always going to
get a little dust on things. The telescope comes in in a clean shipping
container. They air barge it in, and then they start the cleaning.
Before it comes in they clean the whole container really well. It
was just piles and piles of rags. It’s not really rags, they’re
these clean cloths that are, I don’t know, probably $5 or $10
apiece. There’s just piles of them, because they only use them
once, and they’re not very dirty. I’ve taken some of those
home, and they’re great for washing your car. They last forever.
They wash it really well, they clean it, they bring it in.
I was there when they first lifted it out of the shipping container
and placed it onto the lift and turnover fixture. I was there when
they first lifted it up, and I have pictures from the viewing area
of me being reflected off the mirror. When the telescope first got
there, there were lots of moments of awe of looking at it. I must
have given probably 100 people tours by getting friends who work for
NASA, we would all come together and get visitor passes. I gave two
Boy Scout troops a tour, I gave two large groups from my church a
tour, and that was really great to help people to see it.
We’ll get there, but after a while you almost become, “Okay,
there’s the telescope. There’s this $8 billion telescope
sitting in the clean room.” You got used to it. The weeks before
it was leaving, I will admit it was a very sad time, to think my time
on the program was coming to an end. I probably wouldn’t see
the telescope again. I suited up and went into the clean room and
got permission and basically was right underneath the telescope. They
said, “Well, while you’re there, can you do some inspections?”
I found some things on the insulation that were of note, and a couple
of them they had seen already, but I did find something that they
hadn’t noticed. I pretty much just sat in there for a whole
afternoon just looking at it and being with my telescope. It was really
quite nice.
Ross-Nazzal:
What did you find on the insulation that they hadn’t found?
Wells: The
insulation is a black Kapton. It’s a Kapton sheet with a very
black coating. One of the things in orbit is that any corner, I guess
the electrons flying through the space will basically cause an edge
to glow, so you can’t have any exposed edges. Those pieces of
insulation are actually tied together with a clean room string tie.
That string tie also has to not be exposed, so it has these things
called Part C, which are basically these little folded things that
are about a third of an inch by an inch that cover all that up. One
of those seemed to be too loose. It was one of the things that they
would have found anyway. They spent a lot of time inspecting it since
the test. It was a nice time, and now it’s in California sitting
for an extra year now. It launches in 2023 as we now know, and another
$1 billion later.
Moving to the flight test, I talked last time about our goals of aligning
the primary mirror to make sure that we had enough actuator range
on orbit. Our goal was to take these 18 mirrors, which had never been
aligned together at the same time, and to turn them into 1 mirror.
The piston and the tilt between all these mirrors would be the same
to tolerances of numbers like 100 nanometers and 100 nanoradians,
probably more like 50 nanoradians. Our ability to measure the mirror
would be about one-ten-thousandth of a human hair or so. We could
measure to about 10 nanometers the flatness of these mirrors, and
your hair is about 125 microns. If I did the math right, it’s
about one-ten-thousandth. We have a special interferometer that uses
three different lasers to measure the surface of the mirror with three
different wavelengths, two at a time. By combining the data from those
two wavelengths you’re able to measure across two mirrors. Interferometry,
which is what we use, is very good at measuring a flat continuous
surface, a flat mirror or curved mirror that’s one mirror.
When you start having two mirrors it gets confusing to the interferometer.
What happens at that interface between the two mirrors, this interferometer
measures the surface of the mirror with two wavelengths 10 microseconds
apart. Laser one fires and measures it, and laser two fires and measures
it 10 microseconds apart. You combine those two sets of data to understand
both the surface figure of the individual mirrors as well as the height
difference between the mirrors.
I think I mentioned last time we had a lot of challenges with those
lasers. Those lasers, it was difficult for the supplier, 4D Technology,
to find a combination of wavelengths that they needed to solve this
measurement problem. The ones that they ended up using from New Focus
had lifetime problems. We bought some spares at the beginning, [but]
we didn’t buy enough. We basically had to refurbish the lasers.
When we designed the system, we made sure that it would be serviceable.
The interferometer was inside the chamber, the head with the optics,
but the lasers are fiber-fed from outside. The lowest reliability
item we kept outside the chamber. Reliability in being able to conduct
this test successfully was very important. Keeping the things that
could fail, the highest chance of failing, and the things that did
fail, outside the chamber. We had two source modules, and each one
failed once, but we always had a spare, so we were always okay.
When one of them broke, we sent one back to be refurbished. New Focus
had stopped making these lasers and basically said, “I’m
sorry. We don’t have any more. We can’t make them.”
Luckily, NASA has a lot of pull. NASA does a lot of business, they
buy a lot of optics, they buy a lot of lasers. New Focus agreed to
do custom builds and make more of these lasers. For the James Webb
Space Telescope, companies and individuals will do what it takes to
get the job done, and that’s an example of a case where they
got the job done. We always had a spare to use, and we needed them.
We struggled a lot in the early tests trying to understand the performance
of the lasers, and by the time we got to thermal pathfinder we certainly
knew what we were doing. For flight, they behaved very well until
probably the last [few days]. At the end of the test we did some ambient
work, and they started getting a little flaky then. It did allow us
to align these mirrors. We did a coarse alignment and a fine alignment
and then a fine phasing to bring all these mirrors into a single mirror.
We had the luxury during cooldown, during these 30 days, there wasn’t
a whole lot else going on, so we could basically practice. We hadn’t
done it with 18 mirrors yet. We’d done it with two mirrors.
We hadn’t done it with 18. We practiced for probably at least
two weeks before we had to do anything for real, and that was really
important. I requested that time. We needed the support of people
to actually move the mirrors. It was really important to us to get
that done, and it really helped us again, the practice, so that when
it was time to do it for real we could do it, and we could do it successfully,
and we could do it in a reasonable timeframe.
It probably took us a week, two shifts a day, to get all the mirrors
into the interferometer. You need to get all the light through about
a 1-millimeter hole, or so. You’re shining all this light through
the telescope. It comes back, and you’ve got to get them all
tilted into about a 1-millimeter hole, 16 meters away. It was more
challenging than we thought it would be, once again. Once we had done
that, it became much more routine.
The testing, we had to get ready for. One of the important things
for the telescope is how it performs when the temperature of the telescope
changes. On orbit, when it aims from one star to another, the sunshield
angle to the sun will change, so the temperature of the telescope
changes. The predictions say it’s about 0.15 degrees, so a little
over a tenth of a degree. Our goal was to check how much error in
the wavefront was introduced by that 0.15 degrees. That number is
too small. It’s an unmeasurable amount, so we did it over a
3-degree range. We multiplied it by 20x. We went from 0.15 to 3 degrees
and measured for—I think it was maybe two or three days, 24
hours a day, every 3 hours we would measure the mirror. Then they
would look at the progression of those measurements over time.
We had done that in the earlier tests, and we always had challenges
processing the data until thermal pathfinder. The other two, we really
had challenges processing the data. In this last test it worked really
well. The first test, they had a prediction. They had a measurement,
and the lines basically were right on top of each other, so that was
great. We were working 24 hours a day at that point. When you’re
working first shift, second shift, or third shift, it’s hard
to be at the top of your game all the time, and that’s what’s
needed. You’re a little stressed. You’re working long
days, so it’s challenging. It’s mentally challenging,
but we got through it, and that test worked out really well.
Then we had a couple days to phase the mirrors again, and some other
people did some testing. For about two days or so other people were
doing testing. We didn’t have to be here, and that was really
nice. For the thermal team it was 100 days [on], and they staffed
24 hours a day 7 days a week for 100 days. For us it was periods where
we would be on and then periods where we wouldn’t be on. We
had a smaller team as a result, so it was very specialized. The people
that could support us had to have been in one of the previous tests.
They wouldn’t have understood the system and how it worked.
We had James [B.] Hadaway from the University of Arizona; myself;
Joe Cosentino, an engineer from Rochester; Gene Olczak, an engineer,
the architect of the software from Rochester; Mike [Michael] Zarella,
a young engineer from Harris in Rochester; Randal Telfer, who was
at the Space Telescope Science Institute at Johns Hopkins [University,
Baltimore, Maryland]; he was a really big help to the team, and Dave
Chaney from Ball Aerospace [& Technologies]. I guess we had seven
people, and we had a technician, Mark Connelly. The eight of us had
to staff 24 hours a day seven days a week while that was going on.
We did then another thermal distortion test—so we had a first
thermal distortion test and then the second thermal distortion test.
The data in that test did not look right. The straight line went up
and down really badly. The team paying attention to that—and
it wasn’t that I wasn’t paying attention, but we had our
focus, and our focus was to continue to learn how to phase that mirror
better. There were other people who had the bandwidth to think about
these things, and that’s when they started looking into what
would become some real concerns in the test, this instability.
They were seeing wavefront instability 10 or 100 times, probably 100
times larger than we were supposed to see. As a result, teams of people
from the Space Telescope Science Institute—the thermal teams,
there were optical teams, mechanical teams. People all across the
program were starting to look into this.
Our team was, even though we did the measurements, a little bit oblivious
to it because we were busy trying to get the mirror aligned for the
next test. That thermal distortion test ended up not succeeding, and
I’ll get to the causes later. In between these tests, when we
would phase the mirror, there was another team that was putting light
through the whole telescope. We had simulated stars down near the
primary mirror that would bounce through the telescope and bounce
off of three mirrors. Harris built three one-and-a-half-meter autocollimating
flats, basically three large flat mirrors up at the top of the chamber
that were round. Those would allow light to go through the telescope,
reflect off those, and then come back through the telescope and get
imaged right on the science instruments.
One of the goals of building a telescope is to test it as you’re
going to use it. Originally we were going to put an interferometer
in the back of the telescope and shine that interferometer through
and come back. That wouldn’t have tested the instruments themselves.
This concept that people came up with during the replanning of the
testing that we discussed last time, that’s actually going to
continue to be used on future observatories.
We were putting light through the telescope, and the people looking
at that data, the pass-and-a-half team it’s called, because
light passes through the telescope and then comes back, they started
seeing funny things in the data as well. At one point they made a
movie. You could see kind of a sinusoidal, an upward and downward
change in where the spot was, where the image was. People started
understanding that there was a variation every 40 minutes in some
of the data, and then at times there were these large changes. During
the thermal distortion test there was this very large change.
We then worked to get our final phasing done. It was the last week
of August. On the horizon was a tropical storm. There are three shift
reports a day, and each one of those shift reports would report on
whether or not there was any weather in the Gulf or in the Atlantic.
These reports of a storm that ended up becoming Hurricane Harvey became
apparent that that storm could potentially hit us. There were test
planning teams getting ready for that, facility teams getting ready
for that.
Our job was to quickly get that mirror aligned. We needed to get that
mirror aligned. We worked probably for about at that point three days
maybe to get the final alignment done that concluded I think on Friday
the 26th of [August]. That was the Friday that Harvey arrived actually
is when we finished the alignment, the first alignment at stable cryo[genic
temperatures].
We had been aligning the telescope, but it was while it was cooling
down. It would be changing. Each time you would measure, there would
be a little bit of change [in the mirrors because they were still
cooling down]. Early on it was almost impossible to align, in the
first part of that two weeks. Towards the end of that two weeks now
here we are after the second thermal distortion test. We were very
close to stable conditions, stability being defined as 0.1 Kelvin
per hour, so about 2.4 degrees in 24 hours was what we would say,
“Okay, we’ve started stable cryo.” At that point
then the mirror is quite stable. You’re at the 50 Kelvin temperature
or 40 Kelvin temperature. When we would align the mirrors they would
stay in place [because the temperature was stable enough]. Now it
was quite satisfying to see the convergence [in alignment].
The mirrors took a long time to move. One of the reasons it took us
so long, it might take us 5 minutes to take data, it took us about
15 minutes to transfer it, and about maybe half an hour to process
it. Then you think about it for a little while. Between half an hour
and an hour you’d have an answer for what move you wanted to
make. The moves took sometimes as long as 8 hours. If you were making
a really long move it could take [at least] 4 hours. Eight hours probably
was some of the longest moves. One to 4 hours was very common. Then
there was a lot of sitting and waiting around [for the mirrors to
move].
Fortunately and unfortunately, there are lots of checks. When the
mirrors are being moved, it’s constantly checking that a command
has gone out and the command has come back and that the mirror has
moved that amount. There’s a command going out, there’s
a command coming back saying it did it, and then there’s a measurement
that said it moved that much.
If any one of those three things has a hiccup in the software, the
whole move stops and they have to piece together exactly what happened.
Was it the command going out? Was it the command coming back? Was
it resolved? They actually count the number of turns in the motor.
So by counting the number of turns in the motor they can understand
how many times the motor has moved and then they have something called
a LVDT, a linear [variable differential] transducer. Basically as
it moves the voltage changes, and they can measure that [change in
voltage]. If that gets an anomalous reading it stops.
Quite often we would come in and there’d be a mirror [move error]—not
quite often. Once a day it wasn’t surprising for that to happen,
and that would really slow us down. It would give us some time to
analyze the data, but that would really slow us down.
We started this fine phasing process, and I think during that there
were a couple mirror move errors over those let’s say two or
three days. Then we started doing the final alignments. Early on in
the tests we were moving the mirrors in piston and up and down. We
were tilting them, but the mirrors can also be decentered and they
can be clocked. They can be rotated about themselves. There’s
six degrees of freedom on each mirror. There’s six actuators
on each mirror that lie in a hexapod arrangement that give you those
degrees of freedom. There’s one radius of curvature actuator
that helps bend the mirror to give them all the same radius of curvature.
When we started doing the decenter moves, some of those were half-a-millimeter-to-millimeter
moves, quite large. When we’re doing a fine move, it’s
nanometers. We might be moving 100 nanometers or 1 micron. Some of
these though were half a millimeter, 500 microns, or a millimeter
move. Those would take 4 hours. So you’d go out, you’d
get dinner. You’d wait around and hope there wasn’t a
mirror move error. There was a lot of hurry up and wait. You’re
under a lot of pressure once you’ve taken the data to get an
answer. Then you wait.
The mirror phasing was going quite well, and Harvey was coming. My
kids were out of school on that Friday, so I actually wasn’t
there the final day that they did the final alignment. That was the
day Harvey arrived. They did that final alignment. We had another
setting in the software that we’re really never used and didn’t
know that we needed to use. We had that set wrong in the software,
and it ended up [mis]-aligning the mirror in decenter by about half
a millimeter.
We knew it, because we had this amazing—I think I talked about
it last time. In order to measure where the mirrors were externally,
from a big picture, we had a photogrammetry system which took 1,100
pictures and could tell you where the mirrors were to about 100 microns.
You’d know in general where they were. That system takes about
4 hours to take data and about 8 hours to process it. You would take
a measurement, and the next shift would get the answer.
At that next shift we found out that the mirror had been decentered.
I was locked in my house, because we couldn’t go anywhere. We
didn’t flood. We didn’t lose our electricity. We had just
enough food. We had water. We were some of the lucky ones. People
here [at JSC], they went to two shifts a day, so that people would
only have to drive to hotels twice a day. Food became a problem for
people staying at hotels. Restaurants didn’t have food. That
became some of the major concerns of the people staying in hotels.
Some of the hotels, they had water problems.
People were ferrying back and forth and sleeping [in Building 32].
Joe Cosentino got stuck here that Friday night. He didn’t get
back to his hotel. Saturday morning they did some diagnostics on the
mirrors, taking some measurements. He got a ride back to his hotel.
Unfortunately, he left his computer here. So the poor guy was stuck
in his hotel room for [the next] five days without his computer. He
couldn’t do analysis. The poor guy, at least I was at home with
my family.
The team continued to do testing. We stopped testing with the interferometer,
but the other team that was using the simulated starlight continued
testing during all of Harvey and actually got a lot done. That was
I think one of the times that they noticed—it became very obvious
that there was some sort of instability in the telescope that was
much larger than the required value.
When Harvey was done on about August 31st we started coming back.
At that point, we had to find out why the telescope had this instability.
That was the goal really for that portion of the test. People were
still doing functional tests of the instruments and doing other diagnostic
tests that were part of the test plan [but we had to figure out what
was causing the instability].
One of the things in the test planning is you plan for more tests
than you’re going to do, and you’re ready to do any test
hopefully at any time. When there was an [extra] 4-hour block here
[or there you wanted to use the time efficiently]. Mark Waldman, a
former Harris and Kodak engineer, and Tony [L.] Whitman, my boss,
the chief systems engineer from Harris, were the test conductors.
It was their job to figure out given this shift and the following
shift what test they could squeeze in where and how.
Our job became at that point to start measuring this mirror and figure
out what’s going on. We started taking data. Every hour for
8 hours we did, and then we started taking data every 2 minutes. Then
I realized that there would be a way to take data basically continuously.
So then we took data was every 30 seconds or so, and then we figured
out we could tailor it. We were able to take data at any periodicity
we wanted for almost as long as we wanted. We started taking data
sets that had 7,000 frames of data when normally we did 100 or 150.
It would take an entire shift to process that data. It was that data
that helped us see this 40-minute [periodic behavior of instability].
Lo and behold, when we measured the primary mirror we saw this 40-minute
profile. The thermal team said, “Well, what goes at a 40-minute
profile?” They couldn’t find anything that did except
they found a warm electronics compartment that actually had that [time]
period [on its temperature]. There were heaters going on and off with
that exact period. There were four sets of heaters. This was electronics
for the science instruments. There were four of them. One for the
NIRCam [Near Infrared Camera], one for the Mid-Infrared [Imager (MIRI)],
one for the [NIRSpec (Near Infrared Spectrometer)], and one for the
Fine Guidance Sensor. It turned out that that electronics compartment
was set to 1-degree variation, and they just went on and off. We reduced
that down to an eighth of a degree, and it smoothed out that variation
to a great extent. The variation went down to like a 5-minute period
and the peak-to-valley went way down. The data looked a lot better.
They came up with concepts for how to deal with that. It was good
to solve that.
[End
of interview]